Regency FP90 installation manual Standoff

Page 26

INSTALLATION

INSTALLATION

2)Make sure the insulation under the top stand-off is up against the back of the top nailing strip.

3)Fasten the nailing strips to the framing.

4)Install both the left and right side trim (see labels for orientation). The side trims have slotted holes to allow the sides to be adjusted once installed to ensure the top corners will fi t tight. Fasten the trim to the nailing strips with the screws provided, (#8 x 9/16”) in the center of each slot.

5)Attach the top trim. Center it and attach it to the top nailing strip with self drilling screws.

6)Adjust the sides to minimize the overlap at the top corners.

7)The sheathing (up to ½” [13 mm] thick) can then be tucked into the channel of the trim to hide the cut edge (refer to Diagram 2).

STANDOFF

11.000" (279mm)

NON-COMBUSTIBLE (i.e. Cement Board)

2x4 FRAMING

DRYWALL

FINISH COAT

INSTALL TRIM ON NAILING STRIP

THEN TUCK NON-COMBUSTIBLE

SHEATHING INTO POCKET TO

CONCEAL EDGE.

Diagram 2

8)It is recommended that the joints of the sheathing run horizontal from the top corners of the unit rather than vertical. This will reduce the heat exposure to the joints and reduce the chance of the fi nish from cracking.

26

FPI FP90 Wood Fireplace

Image 26
Contents FP90 Wood Fireplace Regency Fireplace Product Table of Contents Safety Label Safety Label for FP90Installation Product DetailsPlease Retain this Manual for Future Reference Dimensions and Specifications Clearances and Height Requirements Installation of Nailing Strips Fireplace Enclosure FramingFraming Details Hearth ExtensionChimney System Considerations Installation ComponentsBefore YOU Start Chase EnclosureInstallation Measurements / Framing Details On EInstalling the Chimney System Assembly StepsInstalling STAND-OFFS SET the Regency FP90 Into PositionOffset Chimney Installation Special NotesInstalling Outside AIR KIT Elevation FT # of Elbows Above SEA LevelGravity AIR Feed KIT Option Wiring the FP90Installing Blower Systems Internal Blower with Thermo-DiscCompleting The Facing Non-self Supporting, Thin Veneer Facades InstallationFinishing Regency FP90 Masonry Retainer Kit Option Finishing Details Completing The MantleGlass Secondary AIR Tube Installation Masonry Liner BricksASH Drawer KIT Ash Drawer Kit InstallationSafety Precautions OptionFAN Installation DiagramMasonry Cover Plate Installation Installation Finishing Trim KIT Installation 60W xAREAStandoff Fireplace Screen Installation Installing the Handles on the ScreenRegency Louver Installation Installing the Top Louver Installing the Bottom LouverExcalibur Faceplate Installation Installing the Facing GuideExcalibur Accent KIT Installation Listings and Code Heatwave KIT not EPA ApprovedGeneral Approvals InformationR90 / EX90 Models InstallationMinimum Framing Clearances All ModelsOperation MaintenanceWiring Diagram Operating Instructions Safety GuidelinesOperating Instructions First FireGlass Removal Replacement MaintenancePlated Finishes Glass Cleaning Door GasketParts List Parts LIST- Firebox & BodyParts LIST- BAFFLES, DOOR, Options FPI FP90 Wood Fireplace Warranty Warranty LifetimeInstaller Please complete the following information