North Star 864 HH installation manual Duct Installation Instructions, Length

Page 59

Optional Equipment (for qualified installers only)

59

Duct Installation Instructions

Determine the route for the heat duct using the illustration below as a guide

NOTE:

Air flow through the duct is affected by length and number of bends. Keep the length and number of bends to the minimum to maximize performance.

Blower Box

When the duct penetrates the fireplace enclosure vertically and the top of the enclosure is within 36” of the top of the fireplace, a firestop spacer that maintains a 1/2” clearance between all sides of the duct and any combustible material must be used.

1/2”

 

Co-Axial Vent

0” Clearance to

 

Combustibles

 

(for intake air

 

20’ Maximum

and exhaust)

 

 

 

Length

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Duct Adapter

 

 

 

 

 

 

Use 10” x 3-1/4” wall stack

(6” Round to 10” x 3-1/4” -

 

 

 

 

 

 

(duct) when passing

included with the power heat

 

 

 

 

 

 

through tight areas.

vent kit)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Attach the blower box to the framing or floorboards of the home following the instructions below.

Wall or Ceiling Mounting

Cut a hole between wall a framing members for the

blower assembly.

b

Attach the wall mounting

c

Slide the blower, with

brackets to the blower box.

wires, into the hole cut

 

in step "a". Attach

 

 

 

with four screws.

5-1/4"

16"*

Mount the bracket to these holes for 2 x 4 walls

Mount the bracket to these holes for 2 x 6 walls

*This blower was designed for framing on 16" centers. Construct additional framing if needed. If the blower is installed prior to the drywall only a 14" opening is required. If installed after the drywall is in place, the drywall to the sides of the blower will need to be patched.

© Travis Industries

4070201

100-01182_002

Image 59
Contents 864 HH Fireplace Listing Details OverviewTable of Contents Safety Warnings Safety PrecautionsSafety Precautions Dimensions Installation OptionsHeating Specifications Additional Items Required Installation OverviewRecommended Installation Procedure Packing ListRequirements for the Commonwealth of Massachusetts Massachusetts RequirementsConverting Fireplace to Top Vent Configuration Top Vent or Rear Vent ConfigurationDo not Over Tighten Screws Converting the Fireplace to Top VentRaised Fireplaces Fireplace Placement RequirementsClearances Minimum 49 Fireplace Enclosure Height Minimum Framing Dimensions Rear Vent ConfigurationMinimum Framing Dimensions Top Vent Configuration Nailing Brackets Corner Installations Rear Vent Configuration Corner Installations Top Vent Configuration Gas Inlet Pressure Gas Line RequirementsFuel Gas Line ConnectionLeft Side Gas Inlet preferred Gas Line LocationElectrical Connection required Wall Switch Installation Wall Switch or Thermostat InstallationWiring Diagram Millivolt System Altitude Considerations Vent RequirementsVent Clearances Approved Vent Vent InstallationRestrictor Position Approved Vent ConfigurationsExhaust Restrictor Adjustment Intake Restrictor Adjustment Diffuser Side View Diffuser Plate AdjustmentExhaust Restrictor Removal 0feet 5feet 22 max Feet 10feet 15feet Rear Vent Configuration with Vertical Termination Feet 21 max 5feet 10feet 15feet Top Vent Configuration with Horizontal TerminationMay use 8 or 6-5/8 Diameter vent see page for Details Top Vent Configuration with Vertical TerminationTermination Requirements Floor Mounted Fireplaces Hearth RequirementsFacing Requirements Drywall InstallationFacing Overview Optional Faceplates Sizing ChartFront View Raised Fireplace with no Hearth Front View Thick Facing with Fireplace Xtrordinair FPX Arched Faces Floor-Mounted Fireplace with Hearth Thick Facing Installation SideMantel Requirements Side View Horizontal Termination Section Firestop Installation Example Build-In with Horizontal TerminationPilot Flame Inspection Steps for Finalizing the InstallationStarting the Pilot Flame Air Shutter Adjustment Finalizing the Installation for qualified installers onlyBased upon the face being used, either Glass Frame Removal and InstallationFinalizing the Installation for qualified installers only Fireback and Grate Installation Right Log Installation Log Set InstallationRear Log Installation Left Log Installation Verify Rear LOG Position Right Twig InstallationEmber Installation Center Twig InstallationFront Twigs Installation LP Conversion Instructions Follow the directions below to replace the orifices Slotted Screwdriver Or T-20 Torx Upper Grill Installation Grill InstallationOption # 2 Remote Thermostat Remote Control Receiver Installation 2 OptionsOption # 1 Remote Thermostat Special Instructions for 864 HH Extra Room Power Heat Duct skuNew Wire Hook-Up Length = Installation OverviewLength Duct Installation InstructionsFloor Mounting Attach the grill and wall adapter, if necessary Wiring Diagram -864TRV OFF Operating InstructionsAccent Light Installation sku Optional Equipment for qualified installers only Accent Light Operation Optional Wall-Mounted RheostatOptional Equipment for qualified installers only Index 68Index