2 General venting

When a sidewall or vertical rooftop combustion air supply system is disconnected for any reason, the air inlet pipe must be resealed to ensure that combustion air will be free of contaminants and supplied in proper volume.

￿ DANGER

Failure to properly seal all joints and seams

 

as required in the air inlet piping may

 

 

result in flue gas recirculation, spillage

 

of flue products and carbon monoxide

 

emissions causing severe personal injury

 

or death.

Vent and air piping

This product has been approved for use with stainless steel vent systems.

Installation & Operation Manual

Air intake/vent connections

1.Combustion Air Intake Connector (FIG. 2-1) - Used to provide combustion air directly to the unit from outdoors. A fitting is provided with the unit for final connection. Combustion air piping must be supported per guidelines listed in the National Mechanical Code, Section 305, Table 305.4 or as local codes dictate.

2. Vent Connector (FIG. 2-1) - Used to provide a passageway for conveying combustion gases to the outside. A transition fitting is provided on the unit for final connection. Vent piping must be supported per the National Building Code, Section 305, Table 305.4 or as local codes dictate.

￿WARNING

NOTICE

Use only the materials, vent systems, and terminations listed in Table 2A. DO NOT mix vent systems of different types or manufacturers, unless listed in this manual. Failure to comply could result in severe personal injury, death, or substantial property damage.

Installations must comply with applicable national, state, and local codes. Stainless steel vent systems must be listed as a UL-1738 approved system for the United States and a ULC-S636 approved system for Canada.

Figure 2-1Combustion Air Adapter

 

 

AIR PIPE

(FIELD SUPPLIED)

SHIPPED LOOSE

 

ADAPTER

 

 

WITH THE BOILER

 

 

 

GASKET

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NOTICE

Installation of a stainless steel vent system

should adhere to the stainless steel vent

 

 

manufacturer’s installation instructions

 

supplied with the vent system.

NOTICE

The Crest is supplied with an integral

FasNSeal vent connector (FIG. 2-1). The

 

 

installer must use a specific vent starter

 

adapter supplied by the vent manufacturer

 

to adapt to different vent systems.

VENT PIPE

(FIELD SUPPLIED)

CONNECTOR

The Crest uses model specific combustion air intake and vent piping sizes as detailed in Tables 2B and 2C on page 17.

NOTICE

Increasing or decreasing combustion air

or vent piping to sizes not specified in this

 

 

manual is not authorized.

Table 2A Approved Stainless Steel Vent Manufacturers

Approved Stainless Steel Vent Manufacturers

Make

Model

ProTech Systems (Simpson Dura-Vent Co.)

FasNSeal Vent

Z-Flex (Nova Flex Group)

Z-Vent

Heat Fab (Selkirk Corporation)

Saf-T Vent

Metal Fab

Corr/Guard

Securities Chimneys International

Secure Seal SS

Schebler Chimney Systems

eVent

16

Image 16
Contents Save this manual for future reference Contents When servicing boiler Please read before proceedingCrest How it works BlowersCrest How it works Models 1.5 2.0 2.5 3.0 Ratings Crest Ahri RatingInstallation must comply with Determine boiler locationBefore locating the boiler, check Provide clearancesProvide air openings to room Flooring and foundationVent and air piping Prevent combustion air contaminationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Remove boiler from wood pallet 7Combustion Air from Outside Single Opening Minimum Recommended Combustion AIR Supply to Equipment Room Direct venting General ventingOptional room air Install vent and combustion air piping Air inlet pipe materialsApproved Stainless Steel Vent Manufacturers Make Model Air intake/vent connectionsRemoving from existing vent Common venting Vertical direct venting Vent/air termination verticalDetermine location Prepare roof penetrationsMultiple vent/air terminations 4Alternate Vertical Terminations with Multiple BoilersSidewall direct venting Vent/air termination sidewallPrepare wall penetrations 2Clearance to Doors and WindowsRoom air 4Multiple Vent Terminations must also comply with FigureHydronic piping Model Circulator sizing20F 40F 60F Near boiler piping components System Multiple Boilers Common Header Primary / Secondary Flow For all equipment and detailing required by local codes Hydronic piping Gas connections Connecting gas supply pipingModel Gas Inlet Size Natural gas Propane GasGAS Piping Size Chart Check inlet gas supplyGas valve replacement Gas PressureInstallation must comply with Field wiringLine voltage connections Enable Outdoor temperature sensorLouver proving switch Low voltage connectionsAuxiliary switch 1 Alarm contactsWiring of the cascade System supply sensorWiring FieldCondensate disposal Condensate drainFreeze protection when used Start-upCheck/control water chemistry Fill and test water systemCheck for gas leaks Check thermostat circuitsInspect condensate system Inspect/check condensate lines and fittingsFinal checks before starting the boiler Start the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Set space heating operation Gas Natural Gas Propane ValveConfiguration of the cascade Verify HWG circulator mode Set HWG target temperatureSet clock Operating information GeneralProtection features Boiler temperature regulation Outdoor reset operation, if usedCascade Sequence of operation Crest control module Home Screen2Main Menu Screen Maintenance Maintenance and annual startup Service technicianOwner maintenance See the Crest User’s Information Manual for InstructionsMaintenance Flue vent system and air piping Check water systemCheck expansion tank Check boiler relief valveCheck ignition ground wiring Check all boiler wiringCheck control settings Check flame signalCleaning boiler heat exchanger Review with ownerHandling ceramic fiber materials Niosh stated First AidDiagrams Integrated Control2Wiring Diagram