Crestron electronic 3.5, 2 Start-up, Check/control water chemistry, Freeze protection when used

Page 40

9 Start-up

Check/control water chemistry

￿CAUTION Do not use petroleum-based cleaning or sealing compounds in the boiler system.

Damage to elastomer seals and gaskets in the system could occur, resulting in substantial property damage.

Hardness less than 7 grains

1.Consult local water treatment companies for hard water areas (above 7 grains hardness).

Chlorine concentration less than 200 ppm

1.Do not fill boiler or operate with water containing chlorine in excess of 200 ppm.

2.Filling with chlorinated fresh water should be acceptable since drinking water chlorine levels are much lower.

3.Do not use the boiler to directly heat swimming pool or spa water.

Test/replace freeze protection fluid

1.For systems using freeze protection fluids, follow fluid manufacturer’s instructions.

2.Freeze protection fluid must be replaced periodically due to degradation of inhibitors over time. Follow all fluid manufacturer’s instructions.

Freeze protection (when used)

1.Determine freeze protection fluid quantity using system water content, following fluid manufacturer’s instructions. Boiler water content is listed on page 6. Remember to include expansion tank water content.

2.Local codes may require a backflow preventer or actual disconnect from city water supply.

3.When using freeze protection fluid with automatic fill, install a water meter to monitor water makeup. Freeze protection fluid may leak before the water begins to leak, causing concentration to drop, reducing the freeze protection level.

Installation & Operation Manual

Fill and test water system

1.Fill system only after ensuring the water meets the requirements of this manual.

2.Close manual and automatic air vents and boiler drain valve.

3.Fill to correct system pressure. Correct pressure will vary with each application.

a.The minimum cold water fill pressure for a commercial system is 12 psi (82.7 kPa).

b.Pressure will rise when boiler is turned on and system water temperature increases.

4.At initial fill and during boiler startup and testing, check system thoroughly for any leaks. Repair all leaks before proceeding further.

￿WARNING Eliminate all system leaks. Continual fresh makeup water will reduce boiler

life. Minerals can build up in the heat exchanger, reducing heat transfer, overheating the heat exchanger, and causing heat exchanger failure.

Purge air from water system

1.Purge air from system:

2.Open automatic air vent (diaphragm-type or bladder- type expansion tank systems only) one turn.

3.Open other vents:

a.Starting on the lowest floor, open air vents one at a time until water squirts out.

b.Repeat with remaining vents.

4.Refill to correct pressure.

40

Image 40
Contents Save this manual for future reference Contents When servicing boiler Please read before proceedingCrest How it works BlowersCrest How it works Models 1.5 2.0 2.5 3.0 Ratings Crest Ahri RatingInstallation must comply with Determine boiler locationBefore locating the boiler, check Provide clearancesProvide air openings to room Flooring and foundationVent and air piping Prevent combustion air contaminationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Remove boiler from wood pallet 7Combustion Air from Outside Single Opening Minimum Recommended Combustion AIR Supply to Equipment Room Direct venting General ventingOptional room air Install vent and combustion air piping Air inlet pipe materialsApproved Stainless Steel Vent Manufacturers Make Model Air intake/vent connectionsRemoving from existing vent Common venting Vertical direct venting Vent/air termination verticalDetermine location Prepare roof penetrationsMultiple vent/air terminations 4Alternate Vertical Terminations with Multiple BoilersSidewall direct venting Vent/air termination sidewallPrepare wall penetrations 2Clearance to Doors and WindowsRoom air 4Multiple Vent Terminations must also comply with FigureHydronic piping Model Circulator sizing20F 40F 60F Near boiler piping components System Multiple Boilers Common Header Primary / Secondary Flow For all equipment and detailing required by local codes Hydronic piping Gas connections Connecting gas supply pipingModel Gas Inlet Size Natural gas Propane GasGAS Piping Size Chart Check inlet gas supplyGas valve replacement Gas PressureInstallation must comply with Field wiringLine voltage connections Enable Outdoor temperature sensorLouver proving switch Low voltage connectionsAuxiliary switch 1 Alarm contactsWiring of the cascade System supply sensorWiring FieldCondensate disposal Condensate drainFreeze protection when used Start-upCheck/control water chemistry Fill and test water systemCheck for gas leaks Check thermostat circuitsInspect condensate system Inspect/check condensate lines and fittingsFinal checks before starting the boiler Start the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Set space heating operation Gas Natural Gas Propane ValveConfiguration of the cascade Verify HWG circulator mode Set HWG target temperatureSet clock Operating information GeneralProtection features Boiler temperature regulation Outdoor reset operation, if usedCascade Sequence of operation Crest control module Home Screen2Main Menu Screen Maintenance Maintenance and annual startup Service technicianOwner maintenance See the Crest User’s Information Manual for InstructionsMaintenance Flue vent system and air piping Check water systemCheck expansion tank Check boiler relief valveCheck ignition ground wiring Check all boiler wiringCheck control settings Check flame signalCleaning boiler heat exchanger Review with ownerHandling ceramic fiber materials Niosh stated First AidDiagrams Integrated Control2Wiring Diagram