Crestron electronic 2 Check for gas leaks, Check thermostat circuits, Inspect condensate system

Page 41

9 Start-up(continued)

Check for gas leaks

Installation & Operation Manual

￿WARNING Propane boilers only – Your propane supplier mixes an odorant with the propane

￿WARNING

￿WARNING

Before starting the boiler, and during initial operation, smell near the floor and around the boiler for gas odorant or any unusual odor. Remove the top access panel and smell the interior of the boiler enclosure. Do not proceed with startup if there is any indication of a gas leak. Use an approved leak detection solution. Repair any leaks at once.

DO NOT adjust or attempt to measure gas valve outlet pressure. The gas valve is factory set for the correct outlet pressure. This setting is suitable for natural gas and propane, requiring no field adjustment. Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death, or substantial property damage.

to make its presence detectable. In some instances, the odorant can fade, and the gas may no longer have an odor. Before startup (and periodically thereafter), have the propane supplier verify the correct odorant level in the gas.

Check thermostat circuit(s)

1.

Disconnect the two external wires connected to the

 

enable terminals on the connection board.

2.

Connect a voltmeter across these two incoming wires.

 

Close each thermostat, zone valve, and relay in the

 

external circuit one at a time and check the voltmeter

 

reading across the incoming wires.

3.

There should NEVER be a voltage reading.

4.

If a voltage does occur under any condition, check and

 

correct the external wiring. (This is a common problem

 

when using 3-wire zone valves.)

Figure 9-1Condensate Trap

FROM CONDENSATE

VENT ON BOILER

FROM CONDENSATE

5. Once the external boiler enable wiring is checked and

corrected if necessary, reconnect the external thermostat

circuit wires to the connection board. Allow the boiler to

cycle.

Inspect condensate system

TO FLOOR DRAIN

DRAIN ON BOILER

OR NEUTRALIZER KIT

Inspect/check condensate lines and fittings

1” PVC / CPVC CONNECTION

1.Inspect the condensate drain line, condensate PVC fittings and condensate trap.

41

Image 41
Contents Save this manual for future reference Contents Please read before proceeding When servicing boilerBlowers Crest How it worksCrest How it works Models 1.5 2.0 2.5 3.0 Crest Ahri Rating RatingsDetermine boiler location Installation must comply withBefore locating the boiler, check Provide clearancesFlooring and foundation Provide air openings to roomVent and air piping Prevent combustion air contaminationAreas likely to have contaminants When using an existing vent system to install a new boilerProducts to avoid When removing a boiler from existing common vent system Remove boiler from wood pallet 7Combustion Air from Outside Single Opening Minimum Recommended Combustion AIR Supply to Equipment Room Optional room air General ventingDirect venting Air inlet pipe materials Install vent and combustion air pipingAir intake/vent connections Approved Stainless Steel Vent Manufacturers Make ModelRemoving from existing vent Common venting Vent/air termination vertical Vertical direct ventingDetermine location Prepare roof penetrations4Alternate Vertical Terminations with Multiple Boilers Multiple vent/air terminationsVent/air termination sidewall Sidewall direct venting2Clearance to Doors and Windows Prepare wall penetrations4Multiple Vent Terminations must also comply with Figure Room airHydronic piping 20F 40F 60F Circulator sizingModel Near boiler piping components System Multiple Boilers Common Header Primary / Secondary Flow For all equipment and detailing required by local codes Hydronic piping Model Gas Inlet Size Connecting gas supply pipingGas connections Propane Gas Natural gasCheck inlet gas supply GAS Piping Size ChartGas Pressure Gas valve replacementLine voltage connections Field wiringInstallation must comply with Outdoor temperature sensor EnableLouver proving switch Low voltage connectionsAlarm contacts Auxiliary switch 1Wiring of the cascade System supply sensorField WiringCondensate drain Condensate disposalStart-up Freeze protection when usedCheck/control water chemistry Fill and test water systemCheck thermostat circuits Check for gas leaksInspect condensate system Inspect/check condensate lines and fittingsStart the boiler Final checks before starting the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Gas Natural Gas Propane Valve Set space heating operationSet clock Verify HWG circulator mode Set HWG target temperatureConfiguration of the cascade General Operating informationProtection features Outdoor reset operation, if used Boiler temperature regulationCascade Sequence of operation Home Screen Crest control module2Main Menu Screen Service technician Maintenance Maintenance and annual startupOwner maintenance See the Crest User’s Information Manual for InstructionsMaintenance Check water system Flue vent system and air pipingCheck expansion tank Check boiler relief valveCheck all boiler wiring Check ignition ground wiringCheck control settings Check flame signalReview with owner Cleaning boiler heat exchangerHandling ceramic fiber materials Niosh stated First AidIntegrated Control Diagrams2Wiring Diagram