Crestron electronic 1.5, 3.5, 2.5 service manual Gas Pressure, Gas valve replacement

Page 34

6 Gas connections

Do not check for gas leaks with an open ￿ WARNING flame -- use the bubble test. Failure to

use the bubble test or check for gas leaks can cause severe personal injury, death, or substantial property damage.

14. Turn on the gas supply at the manual gas valve.

15. Turn the power switch to the “ON” position.

16. Adjust the temperature set point on the control panel of the SMART TOUCH control module to the desired water temperature so the appliance will call for heat.

17. Check burner performance by cycling the system while you observe burner response. The burner should ignite promptly. Flame pattern should be stable. Turn system off and allow burner to cool, then cycle burner again to ensure proper ignition and flame characteristics.

Figure 6-4Inlet Gas Supply Check

Installation & Operation Manual

Gas Pressure

The gas pressure must remain between 4 inches w.c. (.99 kPa) minimum and 14 inches w.c. (3.5 kPa) maximum for Natural gas and between 4 inches w.c. (.99 kPa) minimum and 14 inches w.c. (3.5 kPa) maximum for LP gas during standby (static) mode and while in operating (dynamic) mode. If an in-line regulator is used, it must be a minimum of 10 feet (3 m) from the Crest boiler. It is very important that the gas line is properly purged by the gas supplier or utility company. Failure to properly purge the lines or improper line sizing, will result in ignition failure.

Ignition problems are especially noticeable in NEW LP installations and also in empty tank situations. This can also occur when a utility company shuts off service to an area to provide maintenance to their lines.

Gas valve replacement

The gas valve MUST NOT be replaced with a conventional gas valve under any circumstances. As an additional safety feature, the gas valves have flanged connections to the venturis and blowers.

￿WARNING Failure to follow all precautions could result in fire, explosion, or

death!

￿WARNING DO NOT adjust or attempt to measure gas valve outlet pressure.

Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death, or substantial property damage.

34

Image 34
Contents Save this manual for future reference Contents When servicing boiler Please read before proceedingCrest How it works BlowersCrest How it works Models 1.5 2.0 2.5 3.0 Ratings Crest Ahri RatingBefore locating the boiler, check Installation must comply withDetermine boiler location Provide clearancesVent and air piping Provide air openings to roomFlooring and foundation Prevent combustion air contaminationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Remove boiler from wood pallet 7Combustion Air from Outside Single Opening Minimum Recommended Combustion AIR Supply to Equipment Room Direct venting General ventingOptional room air Install vent and combustion air piping Air inlet pipe materialsApproved Stainless Steel Vent Manufacturers Make Model Air intake/vent connectionsRemoving from existing vent Common venting Determine location Vertical direct ventingVent/air termination vertical Prepare roof penetrationsMultiple vent/air terminations 4Alternate Vertical Terminations with Multiple BoilersSidewall direct venting Vent/air termination sidewallPrepare wall penetrations 2Clearance to Doors and WindowsRoom air 4Multiple Vent Terminations must also comply with FigureHydronic piping Model Circulator sizing20F 40F 60F Near boiler piping components System Multiple Boilers Common Header Primary / Secondary Flow For all equipment and detailing required by local codes Hydronic piping Gas connections Connecting gas supply pipingModel Gas Inlet Size Natural gas Propane GasGAS Piping Size Chart Check inlet gas supplyGas valve replacement Gas PressureInstallation must comply with Field wiringLine voltage connections Louver proving switch EnableOutdoor temperature sensor Low voltage connectionsWiring of the cascade Auxiliary switch 1Alarm contacts System supply sensorWiring FieldCondensate disposal Condensate drainCheck/control water chemistry Freeze protection when usedStart-up Fill and test water systemInspect condensate system Check for gas leaksCheck thermostat circuits Inspect/check condensate lines and fittingsIf boiler does not start correctly Final checks before starting the boilerStart the boiler Check system and boilerFor Your Safety Read Before Operating Set space heating operation Gas Natural Gas Propane ValveConfiguration of the cascade Verify HWG circulator mode Set HWG target temperatureSet clock Operating information GeneralProtection features Boiler temperature regulation Outdoor reset operation, if usedCascade Sequence of operation Crest control module Home Screen2Main Menu Screen Owner maintenance Maintenance Maintenance and annual startupService technician See the Crest User’s Information Manual for InstructionsMaintenance Check expansion tank Flue vent system and air pipingCheck water system Check boiler relief valveCheck control settings Check ignition ground wiringCheck all boiler wiring Check flame signalHandling ceramic fiber materials Cleaning boiler heat exchangerReview with owner Niosh stated First AidDiagrams Integrated Control2Wiring Diagram