8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184

mm)thick.

If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If wall thickness is greater than 7-1/4 in. an extended heat shield will be required.

SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to 194 mm thick).

If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed. If wall thickness is greater than 7-5/8 in. an extended heat shield will be required.

(DVP Pipe Shown)

B. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

SLP pipe - A wall shield firestop must be placed on each side of an interior wall. A minimum 1 1/2 in. (38 mm) overlap of attached heat shields must be maintained.

DVP pipe - A wall shield firestop is required on one side only on interior walls. If your local inspector requires a wall shield firestop on both sides, then both wall shield firestops must have a heat shield attached to them.

See Section 10.L. for information for regarding the installation of a horizontal termination cap.

3 in. (76 mm) top clearance

1 in. (25 mm) clearance around vertical sections

Heat

Shield

Wall

Shield

Firestop

3 in. (76 mm) top clearance *

Heat

Shield

1 in. (25 mm) clearance bottom & sides

Non-Combustible Wall Penetration

If the hole being penetrated is surrounded by noncombus- tible materials such as concrete, a hole with diameter one in. greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield firestop is only required on one side and no heat shield is necessary.

WALL

Heat

Shield

Wall

Shield

Firestop

3 in. (76 mm) top clearance *

Heat

Shield

1 in. (25 mm) clearance bottom & sides

 

10 in.

Vent framing hole.

 

 

12 in.

 

DO NOT PACK WITH

 

INSULATION OR OTHER

MATERIAL.

The center of the framing hole is

1 in. (25mm) above the center of the horizontal vent pipe.

WALL

* When using SLP pipe, minimum clearances from the vent pipe to combustible materi-

als at inside wall firestops are:Top: 2-1/2 in. (64 mm) Bottom: 1/2 in. (13 mm) Sides: 1 in. (25 mm)

Figure 8.1 Horizontal Venting Clearances To Combustible Materi- als

A*

B*

Framing should be constructed of 2 X 4 lumber or heavier.

*Measured to center of pipe.

 

 

A

B

Model

 

Top Vent

Rear Vent

CD4236

inches

42 1/4

27 1/4

 

 

 

mm

1073

692

 

 

 

 

 

CD4842

inches

48 1/4

27 1/4

mm

1226

692

 

Figure 8.3 Wall Penetration

34

Heatilator • Caliber CD Series • 4040-263 Rev N • 11/08

Image 34
Contents Direct Vent Gas Appliance Installation and OperationModels CD4236R CD4842R CD4236LR CD4842LR CD4236IR CD4842IR What to do if you smell gasCongratulations Homeowner Reference InformationInstaller Guide Table of ContentsUser Guide Finishing Appliance SetupTroubleshooting Reference MaterialsWarranty Hearth & Home Technologies Limited Warranty CONDITIONS, Exclusions & Limitation of LiabilityWarranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Operating Instructions Gas Fireplace SafetyYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceFor Your Safety Read Before Lighting Lighting Instructions IPIStanding LightingPilot Frequently Asked Questions After Fireplace is LitRemote Control Maintenance and ServiceMaintenance Tasks-Homeowner Doors, Surrounds, FrontsMaintenance Tasks-Qualified Service Technician Getting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Any such action may cause a fire hazardSelect Appliance Location Framing and ClearancesModel # Clearances Construct the Appliance ChaseRough Opening Model Width Height Depth Mantels Mantel and Wall ProjectionsMantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesMinimum Clearances for Termination Vent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsTop Vent Horizontal Termination Vent DiagramsOne Elbow Two Elbows Two 45 Elbows replacing One 90 ElbowMin Max +H 2 max +H 2+H 3 max Installed Vertically Three ElbowsTop Vent Vertical Termination No Elbow12 ft 3.66 m min 60 ft 18.29 m max Rear Vent Horizontal Termination One 45 ElbowTwo Elbows Rear Vent Vertical Termination Min Ft 1.83 m max 12 ft 3.66 m min 60 ft 18.29 m max Install Vertical Termination Baffle 17 Flat BaffleWall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Installing Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Convert from Top Vent to Rear VentOuter Collar, Remove Four Screws 11 Place Outer Collar on Rear of Appliance 16 Cover Plate-Replace Secure and Level the Appliance 20 Proper Positioning, Leveling And Securing Of AnAssemble Pipe Sections DVP Only Install Vent PipeAttach Pipe to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingCaulk Install RF4-8 SLP-FSInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap InteriorGas Pressure Gas InformationFuel Conversion Gas ConnectionIntellifire Ignition System Wiring Wiring RequirementsStanding Pilot Ignition System Wiring Optional Accessories RequirementsElectrical Service and Repair WSK-MLT-HTLJunction Box Installation Wall Switch Installation for Fan OptionalFacing Material FinishingCombustible Appliance Setup Air Shutter Setting Install Trim and/or SurroundInstall Hood Removing Fixed Glass AssemblySymptom Possible Causes Corrective Action TroubleshootingStanding Pilot Ignition System Symptom Possible Cause Corrective Action Intellifire Ignition System Will not ignite. If the pilot Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP Vent ComponentsBEK DVP-BEK2 DVP-TVHW DVP-TRAP Horizontal Termination CapDVP-HRC-SS Effective SL-2DVP AdapterService Parts CD4236IR, CD4236ILRService CD4236R, CD4236LRIPI Valve Assembly CD4842IR, CD4842ILR CD4842R, CD4842LR IPI Valve Assembly Optional Components Model # Description FFCM36BNThis page intentionally left blank This page intentionally left blank This page intentionally left blank Contact Information