Hearth and Home Technologies CD4236LR Secure the Vent Sections, Disassemble Vent Sections

Page 44

D. Secure the Vent Sections

Vertical runs of DVP pipe must be supported every 8 ft. (2.44 m) after the 25 ft. (7.62 m) maximum unsupported rise.

Vertical runs of SLP pipe must be supported every 8 ft. (2.44 m).

Horizontal sections of vent must be supported every 5 ft. (1.52 m) with a vent support or plumber’s strap.

Wall shield firestops may be used to provide horizontal support.

Vent support or plumber’s strap (spaced 120° apart) may be used for support. See Figures 10.8 and 10.9.

SLP ceiling firestops have tabs that may be used to provide vertical support.

WARNING! Risk of Fire, Explosion or Asphyxi- ation! Improper support may allow vent to sag and separate. Use vent run supports and connect vent sections per installation instructions. DO NOT allow vent to sag below connection point to appliance.

Figure 10.8 Securing Vertical Pipe Sections

Figure 10.9 Securing Horizontal Pipe Sections

E. Disassemble Vent Sections

Rotate either section (see Figure 10.10) so the seams on both pipe sections are aligned as shown in Figure 10.11.

Pull carefully to separate the pieces of pipe.

Figure 10.10 Rotate Seams for Disassembly

Figure 10.11 Align and Disassemble Vent Sections

44

Heatilator • Caliber CD Series • 4040-263 Rev N • 11/08

Image 44
Contents Installation and Operation Models CD4236R CD4842R CD4236LR CD4842LR CD4236IR CD4842IRDirect Vent Gas Appliance What to do if you smell gasCongratulations Homeowner Reference InformationUser Guide Table of ContentsInstaller Guide Appliance Setup TroubleshootingFinishing Reference MaterialsWarranty Hearth & Home Technologies Limited Warranty CONDITIONS, Exclusions & Limitation of LiabilityWarranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Your Fireplace Gas Fireplace SafetyOperating Instructions Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceFor Your Safety Read Before Lighting Lighting Instructions IPIPilot LightingStanding Frequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-HomeownerRemote Control Doors, Surrounds, FrontsMaintenance Tasks-Qualified Service Technician Getting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Any such action may cause a fire hazardModel # Framing and ClearancesSelect Appliance Location Rough Opening Model Width Height Depth Construct the Appliance ChaseClearances Mantel Legs or Wall Projections Mantel and Wall ProjectionsMantels Termination Locations Vent Termination Minimum ClearancesMinimum Clearances for Termination Vent Information and Diagrams Approved PipeVent Table Key Use of ElbowsOne Elbow Vent DiagramsTop Vent Horizontal Termination Min Max +H 2 max +H 2+H 3 max Two 45 Elbows replacing One 90 ElbowTwo Elbows Installed Vertically Three ElbowsTop Vent Vertical Termination No Elbow12 ft 3.66 m min 60 ft 18.29 m max Rear Vent Horizontal Termination One 45 ElbowTwo Elbows Rear Vent Vertical Termination Min Ft 1.83 m max 12 ft 3.66 m min 60 ft 18.29 m max Install Vertical Termination Baffle 17 Flat BaffleVent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Installing Ceiling FirestopVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Convert from Top Vent to Rear VentOuter Collar, Remove Four Screws 11 Place Outer Collar on Rear of Appliance 16 Cover Plate-Replace Secure and Level the Appliance 20 Proper Positioning, Leveling And Securing Of AnInstall Vent Pipe Attach Pipe to the Firebox AssemblyAssemble Pipe Sections DVP Only Assemble Pipe SectionsAssemble Vent Sections SLP Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Caulk Install Metal Roof FlashingAssemble and Install Storm Collar Install RF4-8 SLP-FSHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components SLP only Install Horizontal Termination Cap InteriorGas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements Standing Pilot Ignition System WiringIntellifire Ignition System Wiring Optional Accessories RequirementsElectrical Service and Repair WSK-MLT-HTLJunction Box Installation Wall Switch Installation for Fan OptionalCombustible FinishingFacing Material Appliance Setup Install Trim and/or Surround Install HoodAir Shutter Setting Removing Fixed Glass AssemblyStanding Pilot Ignition System TroubleshootingSymptom Possible Causes Corrective Action Symptom Possible Cause Corrective Action Intellifire Ignition System Will not ignite. If the pilot Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP Vent ComponentsBEK DVP-BEK2 DVP-TVHW DVP-TRAP Horizontal Termination CapDVP-HRC-SS Effective SL-2DVP AdapterService Parts CD4236IR, CD4236ILRService CD4236R, CD4236LRIPI Valve Assembly CD4842IR, CD4842ILR CD4842R, CD4842LR IPI Valve Assembly Optional Components Model # Description FFCM36BNThis page intentionally left blank This page intentionally left blank This page intentionally left blank Contact Information