Mechanical inspection checklist

The mechanical inspection verifies that all mechanical components and connections are secure and tight and ready for start-up and system charging. The inspection ensures that field piping is properly installed to promote oil return to the compressor.

Warning: The equipment is shipped from the factory with a nitrogen holding charge. Remove the nitrogen holding charge using the Schrader valves located on the internal refrigerant piping.

Caution: Improperly installed piping may result in improper operation and possible damage to the cooling unit or surrounding equipment.

Ensure that the:

Fans are turning freely and that the blades are not distorted or bent.

Condensate drain line is at least the size of the drain connection.

Piping joints are tight.

Mechanical connections are tight, including compressor and receiver rotolock connections.

Refrigerant piping size is correct according to the line size table in the installation manual.

Vertical, horizontal, and total run lengths of the liquid, discharge, and suction lines are recorded.

Number of 45- and 90-degree bends in the refrigerant piping are recorded.

Field-installed traps and piping are in accordance with the installation manual and follow proper piping practices.

Refrigerant piping is adequately supported and isolated when necessary.

Field-installed service valves are open.

Pressure relief valve is installed in accordance with the installation manual as well as local and national codes and regulations.

Piping in the building and on the roof is properly insulated.

Covers and guards are in place.

InRow RD 10 kW Air Cooled Operation and Maintenance

5

Image 13
Contents Operation and Maintenance 동봉된 CD 안에 한국어 매뉴얼이 있습니다 American Power Conversion Legal Disclaimer Page Contents Cooling Group Configuration Network Management Card Page Cross-reference symbol used in this manual Symbols used in this manualOverview Safety Initial inspection checklist Inspection ChecklistsEnsure that Electrical inspection checklist Ensure that Mechanical inspection checklistStart-up inspection checklist User interface inspection checklistFinal inspection checklist While the cooling unit is operating, ensure thatCalculating R410A charge Charging With RefrigerantInRow RD 10 kW Air Cooled Operation and Maintenance Charging the equipment Compressor Oil Charge Oil charging procedureInRow RD 10 kW Air Cooled Operation and Maintenance Display Interface OperationScrolling status screens Using the Display InterfaceStatus Screen Name Status Information Displayed Main menu screensNavigating the sub-menus Navigating the main menuPassword entry Using the Path statementStart the cooling unit Cooling unit configuration General ConfigurationStop the cooling unit Configure the cooling group Cooling Group ConfigurationContacts View the state of input and output contactsIdentify the cooling unit Configure ModbusSetpoints Control the EnvironmentPID settings Tune the PID loop Loop Behavior PID Tuning CorrectionControl Method Proportional Integral Derivative Run hours Service intervalsThresholds Date and time Password and time-outDisplay units Adjust display settingsConfigure network Network ConfigurationCooling unit status View Status ReadingsAbout the cooling unit Cooling group statusView the event log Event LogClear the event log View active alarms Respond to AlarmsClear active alarms Alarm messages and suggested actionsThreshlds screen Configure Unit Discrete I/O screen. See page 17 for more TCP/IP configuration methods Quick ConfigurationOverview Bootp & Dhcp configuration APC Device IP Configuration WizardIni file utility NetworkTCP/IPBoot ModeDHCP onlyAdvancedDHCP Cookie Is Remote access to the control console Local access to the control consoleChoose Network from the Control Console menu Control consoleWeb interface Access a Configured Network Management CardTelnet and SSH Modbus Simple Network Management Protocol SnmpRecover From a Lost Password Cleanliness Monthly Preventive MaintenanceEnvironment Electrical MechanicalFunctional tests Semi-Annual Preventive MaintenanceProblem Possible Cause Corrective Action TroubleshootingCorrective Action Problem Possible CausePage Page 990-3212A-001 11/2009 APC Worldwide Customer Support