Burnham MMII manual Recommended Horizontal Vent Installation

Page 15

a.Recommended Installation: slope toward vent terminal. See Figure 11.

b.Alternate Installation (where recommended installation is not practical): slope toward boiler. Horizontal vent drain tee (see Table 7 for part number) required. See Figure 12.

CAUTION

Moisture and ice may form on surfaces around vent terminal. To prevent deterioration, surfaces should be in good repair (sealed, painted etc.)

2.Vent terminal location restricted per following:

a.Minimum 12 inches above grade or normally expected snow accumulation level, or 7 feet above grade if located adjacent to public walkway. Do not install over public walkways or areas where local experience indicates condensate or vapor from Category III appliances creates a nuisance or hazard .

b.Minimum 3 feet above any forced air inlet located within 10 feet.

c.Minimum 1 foot below, 1 foot horizontally from, or 1 foot above any door, openable window, gravity air inlet, or building opening through which flue gases could enter any building (including adjacent buildings).

Figure 11: Recommended Horizontal Vent Installation

Figure 12: Alternate Horizontal Vent Installaltion

15

Image 15
Contents 81404025R13-1/07 Price $3.00 MinutemanTable of Contents Dimensional Drawing Minimum Clearances to Combustible Surfaces Pre-InstallationII. Unpack Boiler III. Water Piping and TrimDo not drop boiler. Do not bump boiler jacket against floor Page Internal Water Piping System Diagram Domestic Hot Water Ratings IV. Domestic Hot Water Performance and PipingRated Input Gas PipingSpecific Gravity Correction Factors Fitting Equivalent LengthsVent/Air Intake Length VI. Venting / Air Intake PipingComponent General GuidelinesBurnham Vent System Components Install Vent ConnectorInstall Vent Pipe, General Install Vent Pipe, Burnham Gasket-Less Vent SystemInstall Vent Pipe, Burnham Gasketed Vent System Burnham Gasketed Vent Joint Detail Horizontal Through Wall Vent InstallationRecommended Horizontal Vent Installation Horizontal Vent Pipe Wall Penetration Vertical Through Roof Vent InstallationInstall Air Intake Pipe Vertical Vent InstallationVII. Electrical Wiring DiagramDo not install an automatic fill valve with this boiler VIII. System Start-upPrepare to check operation Operating Instructions Check Boiler High Limit Adjust gas input rate to boilerGas Flow Rate in Cubic Feet per Hour IX. Service Lubrication Main Burners and Combustion ChamberBurner and Flueway Cleaning Pilot Burner Location Differential Pressure Switch SettingsAvoid Breathing Fiber Particulates and Dust Page Page Cerafelt Gasketing not depicted Repair PartsHeat Exchanger Assembly Canopy/Blower AssemblyPage Page Base Assembly Page Page Jacket Assembly Domestic Water Tank Assembly Miscellaneous Trim and Controls Air Intake Terminal Vent Accessory CartonLimited Warranty