Figure 10B: Burnham Gasketed Vent Joint Detail

b.Align weld seams in pipes and use a slight twisting motion to FULLY insert male end into female end of joint. Ensure bead in male end of pipe is below locking band and rest against the end of the female pipe. Verify the factory- installed gasket is not dislodged or cut.

c.Tighten locking band by HAND with a 5/16" nut driver until snug plus ¼ turn. DO NOT SECURE JOINTS WITH SHEET METAL SCREWS OR POP RIVETS. DO NOT PUNCTURE THE VENT SYSTEM!

d.Once the installation is complete, operate appliance and inspect all joints to ensure that flue gases and/or liquid condensate will not escape.

G.Install Vent Pipe, Burnham Gasket-Less & Gasketed Vent System.

1.Procedure for joining the male end of Burnham Gasket-Less Vent with the female end of Burnham Gasketed Vent. See Figure 10C.

Figure 10C: Burnham Gasket-Less Male and

Gasketed Female Vent Joint Detail

a.Clean the male end of each joint using an alcohol pad to remove any dirt and grease.

b.Apply a continuous ¼ inch bead of sealant around male end of joint no more than 1/8 inch from end.

c.Align weld seams in pipes and use a slight twisting motion to FULLY insert male end into female end of joint. Ensure bead in male end of pipe is below locking band and rest against the end of the female pipe. Verify the factory- installed gasket is not dislodged or cut.

d.Smooth sealant around joint for a continuous seal. Reapply sealant if necessary.

e.Tighten locking band by HAND with a 5/16" nut driver until snug plus ¼ turn. DO NOT SECURE JOINTS WITH SHEET METAL SCREWS OR POP RIVETS. DO NOT PUNCTURE THE VENT SYSTEM!

f.Once the installation is complete, operate appliance and inspect all joints to ensure that flue gases and/or liquid condensate will not escape.

2.Procedure for joining the female end of Burnham Gasket-Less Vent with the male end of Burnham Gasketed Vent. See Figure 10D.

Figure 10D: Burnham Gasket-Less Female and

Gasketed Male Vent Joint Detail

a.Clean joints of pipe or fittings using an alcohol pad to remove any dirt and grease.

b.Slip a locking band over female (bell) end of pipe/fitting.

c.Apply a continuous ¼ inch bead of sealant around male end of joint no more than 1/8 inch from end.

d.Align weld seams in pipes and use a slight twisting motion to FULLY insert male end into female end of joint.

e.Smooth sealant around joint for a continuous seal. Reapply sealant if necessary.

f.Slip the locking band over joint and align closest bead in locking band with bead in male end of pipe.

g.Tighten locking band by HAND with a 5/16" nut driver until snug plus ¼ turn. DO NOT SECURE JOINTS WITH SHEET METAL SCREWS OR POP RIVETS. DO NOT PUNCTURE THE VENT SYSTEM!

h.Once the installation is complete, operate appliance and inspect all joints to ensure that flue gases and/or liquid condensate will not escape.

H.Horizontal (Through Wall) Vent Installation.

1.Maintain minimum ¼ inch per foot slope in horizontal runs. Position weld seams in vent pipes in all horizontal runs at the top to avoid condensate from lying on the seams.

14

Image 14
Contents Minuteman 81404025R13-1/07 Price $3.00Table of Contents Dimensional Drawing Pre-Installation Minimum Clearances to Combustible SurfacesDo not drop boiler. Do not bump boiler jacket against floor II. Unpack BoilerIII. Water Piping and Trim Page Internal Water Piping System Diagram IV. Domestic Hot Water Performance and Piping Domestic Hot Water RatingsGas Piping Rated InputFitting Equivalent Lengths Specific Gravity Correction FactorsGeneral Guidelines VI. Venting / Air Intake PipingComponent Vent/Air Intake LengthInstall Vent Connector Burnham Vent System ComponentsInstall Vent Pipe, Burnham Gasketed Vent System Install Vent Pipe, GeneralInstall Vent Pipe, Burnham Gasket-Less Vent System Horizontal Through Wall Vent Installation Burnham Gasketed Vent Joint DetailRecommended Horizontal Vent Installation Vertical Through Roof Vent Installation Horizontal Vent Pipe Wall PenetrationVertical Vent Installation Install Air Intake PipeWiring Diagram VII. ElectricalPrepare to check operation Do not install an automatic fill valve with this boilerVIII. System Start-up Operating Instructions Adjust gas input rate to boiler Check Boiler High LimitGas Flow Rate in Cubic Feet per Hour IX. Service Main Burners and Combustion Chamber LubricationBurner and Flueway Cleaning Differential Pressure Switch Settings Pilot Burner LocationAvoid Breathing Fiber Particulates and Dust Page Page Canopy/Blower Assembly Repair PartsHeat Exchanger Assembly Cerafelt Gasketing not depictedPage Page Base Assembly Page Page Jacket Assembly Domestic Water Tank Assembly Miscellaneous Trim and Controls Vent Accessory Carton Air Intake TerminalLimited Warranty