C.Install Safety Relief Valve. See Figure 4. Safety Relief Valve must be installed with spindle in vertical position.

Installation of the relief valve must be consistent with the ASME Boiler and Pressure Vessel Code, Section IV.

Figure 4: Recommended Water Piping for Zone Valve Zoned Heating Systems

WARNING

Safety relief valve discharge piping must be piped near floor to eliminate potential of severe burns. Do not pipe in any area

where freez ing could occur. Do not install any shut-off valves.

D.If boiler is used in connection with refrigeration systems, boiler must be installed with chilled medium piped in parallel with the heating boiler using appropriate valves to prevent chilled medium from entering boiler, see Figure 5. Also consult I=B=R Installation and Piping Guides.

Refer to Figure 5a for a diagram of the water piping system inside the Minuteman® II's jacket.

E.If boiler is connected to heating coils located in air handling units where they may be exposed to refrigerated air, boiler piping must be equipped with flow control valves to prevent gravity circulation of boiler water during operation of cooling system.

F.Use a boiler bypass if the boiler is to be operated in a system which has a large volume or excessive radiation where low boiler water temperatures may be encountered (i.e. converted gravity circulation system, etc.).

6

Image 6
Contents Minuteman 81404025R13-1/07 Price $3.00Table of Contents Dimensional Drawing Pre-Installation Minimum Clearances to Combustible SurfacesII. Unpack Boiler III. Water Piping and TrimDo not drop boiler. Do not bump boiler jacket against floor Page Internal Water Piping System Diagram IV. Domestic Hot Water Performance and Piping Domestic Hot Water RatingsGas Piping Rated InputFitting Equivalent Lengths Specific Gravity Correction FactorsGeneral Guidelines VI. Venting / Air Intake PipingComponent Vent/Air Intake LengthInstall Vent Connector Burnham Vent System ComponentsInstall Vent Pipe, General Install Vent Pipe, Burnham Gasket-Less Vent SystemInstall Vent Pipe, Burnham Gasketed Vent System Horizontal Through Wall Vent Installation Burnham Gasketed Vent Joint DetailRecommended Horizontal Vent Installation Vertical Through Roof Vent Installation Horizontal Vent Pipe Wall PenetrationVertical Vent Installation Install Air Intake PipeWiring Diagram VII. ElectricalDo not install an automatic fill valve with this boiler VIII. System Start-upPrepare to check operation Operating Instructions Adjust gas input rate to boiler Check Boiler High LimitGas Flow Rate in Cubic Feet per Hour IX. Service Main Burners and Combustion Chamber LubricationBurner and Flueway Cleaning Differential Pressure Switch Settings Pilot Burner LocationAvoid Breathing Fiber Particulates and Dust Page Page Canopy/Blower Assembly Repair PartsHeat Exchanger Assembly Cerafelt Gasketing not depictedPage Page Base Assembly Page Page Jacket Assembly Domestic Water Tank Assembly Miscellaneous Trim and Controls Vent Accessory Carton Air Intake TerminalLimited Warranty