Ice-O-Matic GEM0956R Remote Condenser Location, Calculation Formula, Calculation Example

Page 13

GEM0650/0956/1256 Remote

Remote Condenser Location

Use the following for planning the placement of the remote condenser relative to the ice machine. Location Limits: Remote condenser location must not exceed ANY of the following:

Maximum rise from the ice machine to the remote condenser is 35 physical feet.

Maximum drop from the ice machine to the remote condenser is 15 physical feet.

Physical line set maximum length is 100 feet.

Calculated line set length maximum is 150 feet.

Calculation Formula

Drop = dd x 6.6 (dd= distance in feet)

Rise = rd x 1.7 (rd = distance in feet)

Horizonal Run = hd x 1 (hd = distance in feet)

Calculation: Drop(s) + Rise(s) + Horizontal Run = dd+rd+hd=Calculated Line Length

Configurations that do NOT meet these requirements must receive written authorization from Ice-O-Matic. This includes multipass or rack system remote condensers.

Do NOT:

Route a line set that rises, then falls, then rises.

Route a line set that falls, then rises, then falls.

Calculation Example 1:

The remote condenser is to be located 5 feet below the ice machine and then 20 feet away horizontally. (5 feet x 6.6=33 feet) + (20 feet) = 53 feet. This location would be acceptable.

Calculation Example 2:

The remote condenser is to be located 35 feet above the ice machine and then 100 feet away horizontally. (35 feet x 1.7=59.5 feet) + (100 feet) = 159.5 feet. 159.5 feet is greater than the 150 maximum is NOT acceptable.

Page 7

Image 13
Contents By Ice-O-Matic Pearl Ice SeriesPage Keep this manual for future reference IntroductionTable Of Contents Inspect Promptly Freight Claim ProcedureVisible Loss or Damage Concealed Loss or DamageGoverning LAW WarrantyFor the Installer GEM0650/0956R GEM1256R Bin Application Ice Machine SpecificationsStorage Bin LocationIce machine Water LimitationsRemote Condenser ERC Dimensions Inches GRC1001 GRC1061 GCR2061Pearl Ice Number Line SetsCalculation Formula Remote Condenser LocationCalculation Example Roof Attachment Remote Condenser LocationPrecharged Line Set Routing Typical Installation Final Connections Coupling Instructions Initial ConnectionsWater Inlet For the PlumberDrains Ice Machine For the Electrician Completed Installation Final Check List Start Up There are no adjustments to make, so replace the panelsPre-Start Inspection Start UpComponent Description Control Board GEM0650/0956/1256 Remote Electrical Sequence Water Operation WaterWater Level Water SystemOperation Refrigeration Refrigeration SchematicLow Condensing Temperature Pump Down Operation Performance Sanitizing and Cleaning Brush in direction of fins Condenser MaintenanceBearing Maintenance Bearing MaintenanceBin Control Sensor Sensor MaintenanceWater Sensor Auger Auger MaintenanceSymptom Possible Cause Probable Correction Service DiagnosisSymptom High pressure cut out check Control System DiagnosticsWater Reservoir Water Reservoir, Bin ControlBin Controls Ice Level Sensors Bearing and Breaker To Remove the Breaker Bearing AssemblyTo Remove the Auger AugerTo Remove the Water Seal Water SealRemoval of the Water Seal To Replace the Water Seal Replacing the Water SealTo Replace the Evaporator EvaporatorTo Reassemble the Evaporator and Auger Gear Motor To Remove and Repair the Gear Motor AssemblyTo Check the Gear Motor To Inspect the Gear MotorFan Blade and Motor To Remove the Condenser Fan Motor AssemblyCharging Procedure Refrigeration ServiceWiring Diagram GEM0650R GEM0650R Wiring DiagramWiring Diagram GEM0956R GEM0956R Wiring DiagramWiring Diagram GEM1256R GEM1256R Wiring DiagramWhat to Do Before Calling for Service Service History