___1. Is the ice system installed indoors in a location where air and water temperatures are controlled, and where they do not exceed the design limitations?

___2. Is there an electrical service within sight of the installed machine? Has the voltage been checked, and compared to nameplate requirements?

___3. Have all the plumbing connections been made and checked for leaks?

___4. Has the machine and bin been leveled?

___5. Is there a minimum of 6 inches clearance at the rear, left and right of the machine for proper service access?

___6. Is the water pressure a minimum of 20 psig?

___7. Has the machine been secured to the bin or dispenser?

___8. Is there a water shut off valve installed near the machine?

___9. Is the remote condenser installed per local codes, and in a place where it has adequate ventilation and minimal solar heat gain?

___10. Has all shipping material and literature (inside front panel) been removed from the units?

___11.Have the remote condenser and pre-charged lines been properly installed?

Condenser Leveled?

Roof Holes Sealed?

Remote condenser

 

Machine Leveled?

secured?

 

 

 

 

 

Plumbing?

Power Supply?

___12. Has the electrical connection between the ice maker and condenser been made?

___13. Verify that the master switch is in the OFF position.

___14. Switch ON the electrical power.

___15. Refer to the Pre-Start instructions, Page 15

Page 14

Image 20
Contents Pearl Ice Series By Ice-O-MaticPage Introduction Keep this manual for future referenceTable Of Contents Freight Claim Procedure Inspect PromptlyVisible Loss or Damage Concealed Loss or DamageWarranty Governing LAWFor the Installer GEM0650/0956R GEM1256R Ice Machine Specifications Bin ApplicationLocation Storage BinIce machine Water LimitationsERC Dimensions Inches GRC1001 GRC1061 GCR2061 Remote CondenserPearl Ice Number Line SetsCalculation Example Remote Condenser LocationCalculation Formula Precharged Line Set Routing Remote Condenser LocationRoof Attachment Typical Installation Coupling Instructions Initial Connections Final ConnectionsDrains Ice Machine For the PlumberWater Inlet For the Electrician Completed Installation Final Check List There are no adjustments to make, so replace the panels Start UpPre-Start Inspection Start UpComponent Description Control Board GEM0650/0956/1256 Remote Electrical Sequence Operation Water WaterWater Level Water SystemRefrigeration Schematic Operation RefrigerationLow Condensing Temperature Pump Down Operation Performance Sanitizing and Cleaning Condenser Maintenance Brush in direction of finsBearing Maintenance Bearing MaintenanceWater Sensor Sensor MaintenanceBin Control Sensor Auger Maintenance AugerService Diagnosis Symptom Possible Cause Probable CorrectionSymptom Control System Diagnostics High pressure cut out checkBin Controls Ice Level Sensors Water Reservoir, Bin ControlWater Reservoir To Remove the Breaker Bearing Assembly Bearing and BreakerAuger To Remove the AugerWater Seal To Remove the Water SealRemoval of the Water Seal To Replace the Water Seal Replacing the Water SealTo Reassemble the Evaporator and Auger EvaporatorTo Replace the Evaporator To Remove and Repair the Gear Motor Assembly Gear MotorTo Check the Gear Motor To Inspect the Gear MotorTo Remove the Condenser Fan Motor Assembly Fan Blade and MotorRefrigeration Service Charging ProcedureGEM0650R Wiring Diagram Wiring Diagram GEM0650RGEM0956R Wiring Diagram Wiring Diagram GEM0956RGEM1256R Wiring Diagram Wiring Diagram GEM1256RService History What to Do Before Calling for Service