WhisperKool XLT 8000, XLT 3000, XLT 4200 Tools Needed, Mark the horizontal lines with a level

Page 10

Sizing the Unit to the Room

MODEL

AMPS

AMPS

PRODUCT DIMENSIONS

ROOM SIZE

 

(starting)

(running)

(H x W x D)

(cubic feet)

 

 

 

 

 

WK 1600

28.32

4.5

15.75" x 14.25" x 17"

300

WK 3000

30.00

6

15.75" x 14.25" x 17"

650

WK 4200

32.00

9

15.75" x 14.25" x 17"

1000

WK 6000

36.00

9.5

22.5" x 14.25" x 21.25"

1500

WK 8000

36.00

10

22.5" x 14.25" x 21.25"

2000

Cutting the Hole for the WhisperKOOL Unit

Tools Needed

Level

Hammer

Screwdriver

Saw

Locate the desired installation location. Using a stud finder, locate two adjacent studs in the walls, and mark them with vertical lines.

• Using a level and a pencil, mark a horizontal line on the wall between the two studs, approximately 1.25 inches (or as close as possible if more than 1.25”) from the ceiling.

• Using a ruler or measuring tape, measure 16 inches down (22.75” for the 6000 and 8000 models), and mark another horizontal line parallel to the first one.

Mark the horizontal lines with a level

Using a saw, cut along the uppermost horizontal line until your saw reaches the stud. Turn the saw around, inserting it into the cut you have just made, and cut toward the opposite stud so that you have a clean horizontal cut between the two studs. Be careful not to cut into the studs themselves. Now make the second horizontal cut from stud to stud on the line 16 inches below the first cut (22.75” for the 6000 and 8000 models).

Page 8

Cut horizontal lines from stud to stud.

XLT 020111

Image 10
Contents XLT Page Table of Contents Owners Please NoteIntroduction What is the WhisperKOOL System?How does the WhisperKOOL System Work? Receiving & Inspecting the Unit Customer Warranty RegistrationContents Receiving and Inspecting the UnitQuick Start Guide Preparing the Wine Cellar Wall & Ceiling FramingMounting the Unit Unobstructed AirflowDoor Ambient Temperature Factor VentilationMark the horizontal lines with a level Tools NeededCut horizontal lines from stud to stud Cut vertical lines along the inside edge of the studs Frame the hole with two-by-four supportsElectrical Outlet InstallationElectrical Needs Sizing Unit to RoomLiquid Measuring Thermostat System Testing UnitApplying Insulation Tape Attach precut foam tape to the unit’s flangeInstalling Thermostat Placement of UnitCondensate Evaporator Switch Using the Whisperkool SystemPower Switch Location of control switchesLiquid Measuring Thermostat System To Use the thermostatButtons PDT JR Operating InstructionsOperation PDT Operating Instructions PDTNormal Operation Maintenance ScheduleMaintenance Humidity ControlDucting Using the Thermostat Controller85F Max Airflow Troubleshooting GuideTry this first Air flows on both sides of the wall Door SealCool air drops and exits beneath door Thermostat Unit MountingMount WhisperKOOL high in the room Icing Up Power RequirementsCondensation DrainlineRepairing Units Removing Rivets Consumer Care ProgramTroubleshooting Checklist General InspectionSpecific Performance Issues Unit is Not Cooling Sufficiently or Not Cooling at AllTemperature Differential Testing Do not Exceed 24HRS on Bypass PlugInlet AIR -- Evaporator Front Side Temperature / Test timeEvaporator Front Side Condenser Back Side Inlet AIR -- Condenser Back SideConclusions Accessories for Cooling Units Technical AssistanceInstallation Terms and Conditions Five 5 Year Compressor Limited WarrantyProduct Warranty Limitations and Exclusions Product Installation RequirementsMaintenance Requirements WhisperKOOL Questions or Additional InformationModelXLTSerial NumberA WhisperKOOL