3.2.4Installation

Preparation of anchor bolts suitable for floor material is your responsibility.

Prepare M12-anchor bolts (4 pcs.) for installation. See “ 7.3 Outline Dimensions” for mounting of the anchor bolts.

zKeep the unit away from vibration. Install the unit on a flat and stable surface.

zRefer to “7.3 Outline Dimensions” for the dimensions of the unit.

„Procedure for Installation

1. The anchor bolts (foundation bolts) are mounted on the level concrete foundation. Lower this unit, inserting the anchor bolts into the unit.

2. Tighten the hexagonal nut to secure the unit onto the foundation.

3. Make sure of no looseness between the anchor bolts and foundation.

Anchor bolt mounting hole (Ø13)

Base

Hexagonal nut

Anchor bolt

Front

Concrete foundation

Fig. 3-5 Procedure for Installation

HRG010-W HRG015-W

3.2 Installation

1st edition : Aug. 2006

3-7

Rev. A: May. 2007

Image 29
Contents Water-refrigerated Thermo cooler To the Customers Table of Contents Chapter Unit Maintenance Error Message and TroubleshootingStartup and Shutdown Chapter DocumentsTOC-3 TOC-4 Before Using this Unit Safety InstructionsDefinitions of Serious injury and Minor injury Level of risk„ Serious injury „ Minor injurySymbols Hazard Warning Label „ High temperature hazardsClassification of risks „ High voltage hazardsType of hazard warning labels Location of hazard warning label Model labelSafety Precautions Safety MeasuresProtective equipment „ For system transportation, installation and removal„ For handling circulating fluid „ For system operationThermo Cooler OFF Emergency MeasuresDisposition of Waste Recovery of refrigerant and compressor oilSystem disposal Material Safety Data Sheet MsdsCirculating fluid disposal Safety Instructions Appearance Appearance and Each Section1 HRG010-W Name of Each SectionName of Each Section HRG015-W 2 HRG015-WName Function Control panelTransport Transport and InstallationForklift Insertion Position and Unit Lifting Transporting with forklift and unit lifting„ HRG010-W-A / HRG015-W-A caster-mounted option Transporting with caster Installation conditions InstallationInstallation location Recommended Installation Location Installation location and maintenance work area„ Procedure for Installation InstallationHRG010-W-A / HRG015-W-A Caster-mounted Option HRG010-W HRG015-W Electrical wiring„ Power supply cable and Gfci breaker Removal of Front Panel „ How to conduct wiringHRG015-W „ Electrical wiring diagram11 Communication Cable Wiring Specifications„ Pipe diameter „ How to install pipingPiping Name Qty „ Recommended piping installationName Size HRG010-W HRG015-W Open the supply valve laid with pipes Supply of circulating fluid„ Disconnection of power supply cable Reinstallation of unitPre-check Startup and ShutdownPreparation for startup Power supplySetting of circulating fluid temperature Additional water supply „ TS switch pump manual operation switchStopping the unit Unit Startup and ShutdownStarting the unit „ Bypass valve Check at startup„ Bypass relieving valve piping set Error Message Error Message TroubleshootingSee 5.3 Alarm Reset for error recovery Troubleshooting„ Error check Alarm Reset Alarm Lamp OFFUndo the screws 6 pcs. to remove the front panel Location of Reset Switch RS Yellow Button „ When the alarm lamp goes out by performing steps 1. to„ Power error check Recovery from Power Failure Power Lamp onUndo the screws 6 pcs. to remove the front panel Switch off the earth leakage breaker once Substances Facility water Circulating fluid spec Spec Unit MaintenanceControl of Water Quality Inspection and Cleaning Inspection method Daily inspectionInspection item „ Cleaning of facility water „ Replacement of circulating fluidQuarterly inspection Biannual inspection„ Antifreeze function automatic pump operation Check during wintertime„ Antifreeze of circulating fluid Part number Qty Remarks ConsumablesLong-term Storage Documents Standard SpecificationsHRG010-W HRG015-W „ Caster Optional Specifications„ Gfci breaker „ Communication2 HRG010-W-A, HRG015-W-A Outline Dimensions1 HRG010-W, HRG015-W Electric CircuitElectric Circuit HRG010-W-BC, HRG015-W-BC 2 HRG010-W-BC, HRG015-W-BC„ HRG010-W, HRG015-W Flow ChartIN/OUT Thermo Cooler HRG010-W / WRG015-W Daily Inspection SheetProduct Warranty