Sierra Monitor Corporation HRG015-W, HRG010-W operation manual Additional water supply

Page 41

HRX-OM-J049-A

Chapter 4 Startup and Shutdown

4.2.3Additional water supply

„[TS] switch (pump manual operation switch)

This unit has the [TS] switch (pump manual operation switch) to purge air from the circulating fluid circuit at initial startup. Remove the front panel, and purge air according to the procedures given below.

[TS] switch (green)

Front

Fig. 4-3 [TS] switch (pump manual operation switch)

1. Press the [TS] switch for several seconds, monitoring the fluid level gauge.

Air is purged from the pipe, and the fluid level is lowered.

zThe [ALARM1] lamp comes on (error). The lamp goes out with the press of the [RS] switch after the circulating fluid reaches the range specified on the level indicator.

zSee “Chapter 5 Error Message and Troubleshooting” for error messages.

Control panel

Reset SW [RS] (yellow button)

Front

Fig. 4-4 Location of Reset Switch (Yellow Button)

2. Supply the circulating fluid again according to section “3.2.7Supply of circulating fluid”.

If leakage occurs due to faulty piping including an opened fitting of eternal piping, stop manual operation of the pump and fix the leak.

HRG010-W HRG015-W

4.2 Preparation for startup

1st edition : Aug. 2006

4-3

Rev. A: May. 2007

Image 41
Contents Water-refrigerated Thermo cooler To the Customers Table of Contents Chapter Unit Maintenance Error Message and TroubleshootingStartup and Shutdown Chapter DocumentsTOC-3 TOC-4 Before Using this Unit Safety InstructionsDefinitions of Serious injury and Minor injury Level of risk„ Serious injury „ Minor injurySymbols Hazard Warning Label „ High temperature hazardsClassification of risks „ High voltage hazardsType of hazard warning labels Location of hazard warning label Model labelSafety Precautions Safety MeasuresProtective equipment „ For system transportation, installation and removal„ For handling circulating fluid „ For system operationThermo Cooler OFF Emergency MeasuresDisposition of Waste Recovery of refrigerant and compressor oilSystem disposal Material Safety Data Sheet MsdsCirculating fluid disposal Safety Instructions Appearance Appearance and Each Section1 HRG010-W Name of Each SectionName of Each Section HRG015-W 2 HRG015-WName Function Control panelTransport Transport and InstallationForklift Insertion Position and Unit Lifting Transporting with forklift and unit lifting„ HRG010-W-A / HRG015-W-A caster-mounted option Transporting with casterInstallation conditions InstallationInstallation location Recommended Installation Location Installation location and maintenance work area„ Procedure for Installation InstallationHRG010-W-A / HRG015-W-A Caster-mounted Option HRG010-W HRG015-W Electrical wiring„ Power supply cable and Gfci breaker Removal of Front Panel „ How to conduct wiringHRG015-W „ Electrical wiring diagram11 Communication Cable Wiring Specifications„ Pipe diameter „ How to install pipingPiping Name Qty „ Recommended piping installationName Size HRG010-W HRG015-W Open the supply valve laid with pipes Supply of circulating fluid „ Disconnection of power supply cable Reinstallation of unitPre-check Startup and ShutdownPreparation for startup Power supplySetting of circulating fluid temperature Additional water supply „ TS switch pump manual operation switchStopping the unit Unit Startup and ShutdownStarting the unit „ Bypass valve Check at startup„ Bypass relieving valve piping set Error Message Error Message TroubleshootingSee 5.3 Alarm Reset for error recovery Troubleshooting„ Error check Alarm Reset Alarm Lamp OFFUndo the screws 6 pcs. to remove the front panel Location of Reset Switch RS Yellow Button „ When the alarm lamp goes out by performing steps 1. to„ Power error check Recovery from Power Failure Power Lamp onUndo the screws 6 pcs. to remove the front panel Switch off the earth leakage breaker once Substances Facility water Circulating fluid spec Spec Unit MaintenanceControl of Water Quality Inspection and Cleaning Inspection method Daily inspectionInspection item „ Cleaning of facility water „ Replacement of circulating fluidQuarterly inspection Biannual inspection„ Antifreeze function automatic pump operation Check during wintertime„ Antifreeze of circulating fluid Part number Qty Remarks ConsumablesLong-term Storage Documents Standard SpecificationsHRG010-W HRG015-W „ Caster Optional Specifications„ Gfci breaker „ Communication2 HRG010-W-A, HRG015-W-A Outline Dimensions1 HRG010-W, HRG015-W Electric CircuitElectric Circuit HRG010-W-BC, HRG015-W-BC 2 HRG010-W-BC, HRG015-W-BC„ HRG010-W, HRG015-W Flow ChartIN/OUT Thermo Cooler HRG010-W / WRG015-W Daily Inspection SheetProduct Warranty