American Panel BCIP, BCCP-1, BCCP-2, AP40BC250-2-12, AP40BC250-12 manual B. Installation

Page 6
INSTALLATION

INSTALLATION

B. Installation

American Panel Corporation equipment has been shipped in a package designed to sufficiently protect from damage under normal shipping circumstances.

Upon receiving the shipment, carefully inspect the package for visible damage and check the number of packages against the Bill of Lading. Notify the carrier immediately of any shortage or damage to your shipment. Claims must be filed promptly with the carrier.

After receipt of shipment, carefully and safely remove the unit from the package. Check the containing of the package against the packing list.

Under no circumstances may a damaged piece of equipment be returned to American Panel Corporation without first obtaining written permission.

To assure proper installation carefully read and comply with the following instructions.

B.1. Initial Cabinet Preparation

Note: When following the installation instructions consider that the fan assembly frame will be inserted into door hinge side of cabinet and the coil assembly frame will be inserted in the door latch side of cabinet.

Check if the cabinet was provided with penetrations to accommodate the refrigeration pipes (2-1/2” hole) and the drainpipe (1-1/2” hole). If the cabinet is provided with penetrations proceed with the installation of the coil assembly frame. Otherwise follow the next steps:

1.Measure location of drainpipe on drain pan (see PHOTO #1) where it will extend behind the Coil Assembly Frame (see PHOTO #3, page 9). Properly cut a corresponding 1 ½” hole in the rear corner panel to receive the drainpipe (see DRAWING #1).

PHOTO # 1

DRAWING # 1

2.Measure and locate the refrigeration lines on the coil assembly frame and properly drill corresponding 2 ½” holes in the ceiling side or rear panels to accommodate 1 1/8” and ½” pipes.

3.Install the air deflectors on the top corners (above the fan and coil frames) using the provided self-taping stainless steel screws.

4

Image 6
Contents 5800 S.E. 78th Street, Ocala, Florida Phone 352 245-7055 Fax 352 E-mail service@americanpanel.comAmerican Panel Corporation REV. C5800 S.E. 78 th Street, Ocala, Florida Phone 352 245-7055 Fax 352 “Our reputation rests on the steadfast pursuit of your satisfaction”INDEX IndexINTRODUCTION A. IntroductionCONTROLLER INSTALLATION B. InstallationB.2. Single Unit Installation AP40BC250-12 And BCCP-1 INSTALLATION PHOTO #2 DRAWING # PHOTO #3 B.2.3. Electrical Connections PLUG/CONNECTOR DESTINATION COLOR CODE CHARTPLUG/CONNECTOR CABLE/WIREPHOTO #4 PHOTO #5 PHOTO #6 PHOTO #7 Door magnetic switch on the left Magnet on the right PHOTO #8C. Refrigeration Unit Installation i CABINETii AIR COOLED electrical power supplies FIG # VERIFYING CORRECT INSTALLATION CONDENSATE DRAINAGE CONNECTIONPREPARATION PROGRAMMINGD. Programming The Controller WARNINGS Automatic ModeD.3. Programming Modes a three button combination using , , , , . For example, press PROGRAMMING PROGRAMMING PROGRAMMING PROGRAMMING D.5.4. Parameter Programming For UV Cycle The Parameter Programming is now complete E. Printer Optional PROGRAMMING Panning OPERATINGF. Operating And Maintaining The Unit LoadingThe food temperature screen air temperature screenthe food temperature screen air temperature screenOPERATING F.2.6. Error Messages And Troubleshooting Preventive Maintenance As needed MAINTENANCEDaily Cleaning WarningsWARRANTY contractor. It is not covered by this WarrantyAUTO APPENDIXESAppendixes MANUALAppendix 2 Electrical Schematic Appendix 3 Electrical Schematic Part DescriptionNumber ƒ Click on Sales & Service ƒ Click on Dealer Locator Appendix 5 Ordering Printer Supplies Ribbon & PaperE-mail service@americanpanel.com American Panel Corporation5800 S.E. 78th Street, Ocala, Florida Phone 352 245-7055 Fax 352