SNFS

Power Up Sequence

To power up StorNext FS as part of a Fibre Channel environment:

Step 1 Enable FC fabric switches, if present.

Step 2 Enable FC hubs, if present.

Step 3 Enable FC disk arrays or disk drives.

Step 4 Start the StorNext FS server.

StorNext

FS server