Concrete Foundation Pad
Installation
A concrete foundation and pad may be constructed to elevate the machines. Care must be exercised in the design of the foundation pad due to the force exerted by the machine during extract. This concrete base (recommended not to exceed 8 inches [20.32 cm]) (above existing floor) must be poured, reinforced with rebar and tied to the existing 6 inch (153 mm) (for 35 and 60
IMPORTANT: Do NOT install a pad on top of the existing floor. The foundation and pad must be constructed and tied together as one piece.
If the existing floor is not reinforced concrete at least 6 inch (153 mm) (for 35 and 60
1.Cut a hole larger on all sides than the machine base through the existing floor. The foundation should extend a minimum of 9 inches (229 mm) for 35 models or 12 inches (305 mm) for 60 - 150 models out from the machine on all sides.
2.Excavate to a depth of 18 inches (457 mm) from the top of the existing floor.
3.Produce a
4.If installing a foundation and pad, prepare a form for the
5.Refill with compacted fill dirt, making sure to allow for correct concrete thickness.
Specifications and Dimensions
6.Wet the hole around the cement foundation well and brush the exposed foundation with cement grout.
7.Completely fill with a minimum of 6 inch (153 mm) (for 35 and 60
8.For new foundations only a
9.Allow concrete to dry.
10.Proceed to Machine Mounting and Grouting section.
NOTE: If the
For technical assistance, contact your local distributor or call Alliance Laundry Systems at (920)