Options/Accessories

The following can be carried out on any UPS

13. Press

on the keyboard

14 Press

or

on the keyboard until

15. Press

on the keyboard

16.Press on the keyboard

All the systems will transfer to normal operation.

Display shows

Bypass operation

:YES

Bypass operation :NO

Normal operation load power xx%

No lamps on the bypass panel lights any longer

6.2.4 Isolating One UPS for Service/Maintenance

In a redundant system, one UPS may be isolated for service/maintenance without affecting other UPSs.

1.Check that remaining UPS(s) is capable of carrying the load in the event that one UPS is isolated

2.Switch off system to be isolated for maintenance purposes by pushing green “ON” and red “OFF” buttons simultaneously

3.To disconnect battery, mains and output, open battery MCCB/fuse and set input switch (Q001) and output switch (Q002) to position “0”

With Q002 in position “0”, UPS will be operational and may be tested as a single system without affecting other parallel UPS(s).

990-4050

66

Installation Guide APC Silcon 10-40kW 400V UPS

Page 66
Image 66
APC 10-40KW 400V UPS manual Following can be carried out on any UPS, Isolating One UPS for Service/Maintenance