Step 7. Attach the fan wires to the ceiling fixture outlet box wiring by placing the bare ends of the wires side by side and then securing with a wire nut. Test that the connection is secure by pulling on the wire nut. Connect in this order:

GREEN leads from mounting plate and downrod assembly of fan to GROUND conductor of power source. Secure with wire nut.

WHITE wire from fan to white NEUTRAL wire in ceiling fixture outlet box. Secure with wire nut.

BLACK power wire from fan to BLACK power wire in ceiling outlet box. Secure with wire nut.

NOTE: If the color of your ceiling wires differs from that described, consult an electrician.

WIRE NUT

2 BLACK WIRES

2 WHITE WIRES

3 GREEN WIRES

Canopy Hatch and cover ring Installation

Step 8a. Tuck the wires into the canopy with the wire nuts pointed upwards, so that the WHITE and BLACK wires are on opposite sides of the canopy and all wires are clear of the canopy opening.

Step 8b. Install the canopy hatch with the last canopy screw and lock washer using the provided screwdriver. To do this, tilt the fan body away from the hatch opening. Tighten the screws firmly.

Step 8c. Straighten the fan, then check to ensure there is no movement between the canopy and the ceiling or the Perma•Lockdownrod and the ball assembly.

Step 8d. Locate the locking pins on the canopy cover ring as shown in Figure #2. Lift up on the canopy cover ring and guide the two (2) locking pins into the two (2) locking holes, then snap the canopy cover in to place as shown in Figure #3.

CANOPYCanopy Hatch and cover ring Installation

HATCH

CANOPY

SCREW &

WASHER

Figure #1

Figure #2 CANOPY

CANOPY

COVER

RING

LOCKING

HOLES

LOCKING PINS

Figure #2

Figure #3