FIGURE 9
PLENUM INSTALLATION
Note: PROPER HEADER AND WALL PENETRATION MUST CONFORM TO ALL NATIONAL AND LOCAL BUILDING CODES.
Proper
Flashing
Proper
Caulking
Proper Header
Outside
Wall
Caulk all 8 flange corners and unused holes
Inside Wall Plenum (Part B)
Install anchor screws approximately four inches from the top and bottom of the plenum. Do not make pene- tration through the top or bottom of the plenum
Proper Caulking
Architectural louver VPAL2 mounted on the outside wall plenum (Part A)
Proper Flashing
AFTER THE ROUGH CUT OPENING IS PREPARED, YOU ARE READY TO ASSEMBLE THE TWO WALL PLENUM PARTS. BEFORE CAULKING AND PERMANENT ATTACHMENT, DRY fiT THE OUTSIDE PLENUM INTO THE ROUGH OPENING AND CHECK FOR fiT AND LEVEL. CAULK (SILICONE RECOMMENDED ) THE PARTS WELL AND INSERT THEM INTO THE WALL AS SHOWN.
A)APPLY CAULK AND INSERT OUTSIDE PART A INTO THE HOLE.
B)APPLY CAULK AND INSERT INSIDE PART B INTO PART A. BE SURE THAT PART A DOES NOT BACK OUT OF THE WALL HOLE.