3 CUT THE OPENING

Installation Instructions

UNDER-CABINET INSTALLATION

3 CUT THE OPENING

If the cabinet has been installed, remove it from the wall.

Use the Top Cabinet Template to locate and cut a hole in the bottom of the cabinet.

If necessary, place the template on top of the cabinet to accurately cut a matching hole.

Install the cabinet onto the wall.

The cabinet must be firmly secured to the wall and be capable of supporting 100 lbs.

INSTALL WOOD BLOCKS IF NECESSARY

Install filler blocks whenever the cabinet frame hangs below the cabinet bottom.

Install filler blocks whenever the cabinet bottom is less than 3/4” thick.

Install the filler blocks on each side of the cutout. The filler blocks will accept the hood mounting screws.

NOTE: Additional filler blocks may be required along the outside edges to accept the outside screws. See Step 5.

Cabinet Frame.

Cabinet Bottom Shelf

Filler Block

Equivalent to

Depth of Cabinet

Recess

Top of Vent

Hood

IMPORTANT: If filler blocks are not used, the hood may not be secured to the cabinet.

4 INSTALL SIDE “L” BRACKETS

Install 2 screws in

each bracket

Install the “L” brackets onto each side of the cutout. The wide flat portion should be on top of the opening. Install 2 screws into the top of each bracket.

5 REMOVE SIDE SCREW

The top center screw on both sides of the hood can be used to close up any noticeable gaps at the outside edges. See illustration.

Remove screw cover

and screw

Remove the center screw cover and screw on each side as shown.