IBM AA-RWF3A-TE manual Installing the Plenum if required

Models: AA-RWF3A-TE

1 159
Download 159 pages 29.86 Kb
Page 49
Image 49
Installing the Plenum (if required)

Installing the Plenum (if required)

If installing one of the following SAN switches only, you must install the plenum that ships in the accessory kit with the rack mount hardware:

4/8 SAN Switch

4/16 SAN Switch

4/32B SAN Switch

To install the plenum:

1.Place the device (with inner rails attached) on a flat surface, see Figure 17.

2.Obtain the plenum and four 8-32 x .312 Phillips Pan-head SEMs screws from the accessory kit.

3.For each inner rail (Left and Right) use one screw hole marked 8 and one screw hole marked 16 to attach the plenum.

Manual background CAUTION:

Verify that the open end of the plenum faces the rear of the switch. For example, when installed properly you should see the plenum’s air vent holes on one side, and the front panel of the switch on the other.

SAN Switch installation guide

49

Page 49
Image 49
IBM AA-RWF3A-TE manual Installing the Plenum if required