Lennox International Inc 506510-01 installation instructions Flushing the System

Models: Dave Lennox Signature Collection XC17 Air Conditioner 506510-01

1 49
Download 49 pages 11.15 Kb
Page 14
Image 14
Flushing the System

Flushing the System

FLUSHING

 

TYPICAL CHECK EXPANSION VALVE

 

 

 

(Uncased Coil Shown)

 

 

 

 

 

 

REMOVAL PROCEDURE

 

LINE SET AND INDOOR COIL (1 OF 2)

 

 

 

STUB END

 

 

TWO PIECE PATCH PLATE

LIQUID LINE

 

CHECK

 

 

 

 

 

 

 

 

(UNCASED COIL ONLY)

 

 

 

 

 

 

ORIFICE

 

EXPANSION

 

TYPICAL FIXED ORIFICE REMOVAL PROCEDURE

 

 

 

 

 

 

DISTRIBUTOR

 

HOUSING

 

VALVE

 

1(Uncased Coil Shown)

 

 

 

 

 

 

 

 

 

TUBES

 

 

 

TEFLON

DISTRIBUTOR TUBES

 

 

 

 

 

 

 

RING

LIQUID LINE ORIFICE HOUSING

 

 

 

 

 

 

 

 

 

 

 

 

 

TEFLON

 

 

TEFLON RING

 

 

 

 

RING

 

SENSING

 

 

 

 

 

 

 

 

FIXED ORIFICE

 

 

 

 

 

 

LINE

 

BRASS NUT

 

OR

 

 

 

 

 

 

 

 

DISTRIBUTOR

EQUALIZER

 

 

 

 

 

ASSEMBLY

 

 

 

 

 

 

 

LINE

 

 

 

 

 

 

 

 

 

 

 

DISTRIBUTOR

 

 

 

 

 

 

LIQUID LINE

 

ASSEMBLY

 

 

 

 

 

 

 

 

 

 

 

 

 

ASSEMBLY WITH

 

REMOVE AND DISCARD

 

 

 

 

 

 

 

 

 

 

 

 

 

BRASS NUT

 

WHITE TEFLON SEAL (IF

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PRESENT)

LIQUID LINE ASSEMBLY

 

 

 

 

 

 

 

(INCLUDES STRAINER)

MALE EQUALIZER

 

 

 

 

 

 

 

 

 

A On fully cased coils, remove the coil access and plumbing panels.

LINE FITTING

VAPOR

 

 

 

 

LIQUID

B Remove any shipping clamps holding the liquid line and distributor

SENSING BULB

LINE

LINE

 

 

 

 

 

 

 

assembly.

 

 

A On fully cased coils, remove the coil access and plumbing panels.

C Using two wrenches, disconnect liquid line from liquid line orifice

B Remove any shipping clamps holding the liquid line and distributor as-

housing. Take care not to twist or damage distributor tubes during

sembly.

 

 

 

 

 

this process.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

D Remove and discard fixed orifice, valve stem assembly if present

C Disconnect the equalizer line from the check expansion valve equaliz-

er line fitting on the vapor line.

 

 

 

and Teflon washer as illustrated above.

 

 

 

 

 

 

 

 

 

 

 

 

 

E Use a field−provided fitting to temporary reconnect the liquid line to

D Remove the vapor line sensing bulb.

 

 

 

 

 

 

 

 

the indoor unit’s liquid line orifice housing.

 

 

E Disconnect the liquid line from the check expansion valve at the liquid

 

 

 

line assembly.

 

 

 

 

 

2CONNECT GAUGES AND EQUIPMENT FOR FLUSHING PROCEDURE

 

 

INVERTED HCFC−22

GAUGE

 

 

CYLINDER CONTAINS

MANIFOLD

 

 

CLEAN HCFC−22 TO BE

 

 

 

A

USED FOR FLUSHING.

 

 

 

 

1

LOW

HIGH

 

 

 

VAPOR LINE

NEW

 

 

SERVICE VALVE

OUTDOOR

 

 

 

 

UNIT

 

 

 

 

OPENED

CLOSED

EXISTING

 

 

 

INDOOR unit

B

 

 

 

 

 

 

LIQUID LINE SERVICE

 

 

VALVE

 

 

 

RECOVERY

 

 

 

 

CYLINDER

 

 

TANK

 

 

 

 

RETURN

 

 

VAPOR LIQUID

C

DISCHARGE

 

D

 

 

INLET

 

 

 

 

 

 

 

RECOVERY MACHINE

AInverted HCFC−22 cylinder with clean refrigerant to the vapor service valve.

BHCFC−22 gauge set (low side) to the liquid line valve.

CHCFC−22 gauge set center port to inlet on the recovery machine with an empty recovery tank to the gauge set.

D Connect recovery tank to recovery machines per machine instructions.

FDisconnect the check expansion valve from the liquid line orifice hous- ing. Take care not to twist or damage distributor tubes during this pro- cess.

GRemove and discard check expansion valve and the two Teflon rings.

HUse a field−provided fitting to temporary reconnect the liquid line to the indoor unit’s liquid line orifice housing.

CAUTION

tems which contain contaminants (Example compressor burn out.

3FLUSHING LINE SET

The line set and indoor unit coil must be flushed with at least the same amount of clean refrigerant that previously charged the sys-

tem. Check the charge in the flushing cylinder before proceeding.

B

ASet the recovery machine for liquid recovery and start the recov- ery machine. Open the gauge set valves to allow the recovery machine to pull a vacuum on the existing system line set and in- door unit coil.

BInvert the cylinder of clean HCFC−22 and open its valve to allow liquid refrigerant to flow into the system through the vapor line valve. Allow the refrigerant to pass from the cylinder and through the line set and the indoor unit coil before it enters the recovery machine.

CAfter all of the liquid refrigerant has been recovered, switch the recovery machine to vapor recovery so that all of the HCFC−22 vapor is recovered. Allow the recovery machine to pull down to 0 the system.

DClose the valve on the inverted HCFC−22 drum and the gauge set valves. Pump the remaining refrigerant out of the recovery machine and turn the machine off.

Page 14

506510−01

Page 14
Image 14
Lennox International Inc 506510-01, Dave Lennox Signature Collection XC17 Air Conditioner Flushing the System