FLUSHING LINE SET AND INDOOR COIL (2 OF 2)

4TYPICAL CHECK EXPANSION VALVE INSTALLATION PROCEDURE

This outdoor unit is designed for use in systems that use check expansion valve metering device. See the Lennox XC17 Engineering Handbook for approved check expansion valve kit match−ups and application information.

TWO PIECE PATCH PLATE (UNCASED COIL ONLY)

DISTRIBUTOR

TUBES

(Uncased Coil Shown)

LIQUID LINE STUB

ORIFICE END CHECK

HOUSINGEXPANSION VALVE

The check expansion valve unit can be installed internal or external to the indoor coil. In applications where an uncased coil is being installed in a field−provided plenum, install the check expansion valve in a manner that will provide access for field servicing of the check expansion valve. Refer to below illustration for reference during installation of check expansion valve unit.

TEFLON

RING

 

11

12

1

1/2 TURN

 

 

 

 

10

 

 

2

9

 

 

 

43

8

7

6

5

 

 

 

A Remove the field−provided fitting that temporary reconnected the liquid

TEFLON

 

line to the indoor unit’s distributor assembly.

SENSING

B Install one of the provided Teflon rings around the stubbed end of the

RING

 

LINE

check expansion valve and lightly lubricate the connector threads and

 

 

expose surface of the Teflon ring with refrigerant oil.

DISTRIBUTOREQUALIZER

ASSEMBLY LINE

LIQUID LINE

ASSEMBLY WITH

BRASS NUT

MALE EQUALIZER LINE

VAPOR

FITTING (SEE

LINE

EQUALIZER LINE

 

INSTALLATION FOR

LIQUID LINE

FURTHER DETAILS)

 

SENSING BULB INSULATION IS REQUIRED

IF MOUNTED EXTERNAL TO THE COIL

CASING. SENSING BULB INSTALLATION

FOR BULB POSITIONING.

CAttach the stubbed end of the check expansion valve to the liquid line orifice housing. Finger tighten and use an appropriately sized wrench to turn an additional 1/2 turn clockwise as illustrated in the figure above, or 20 ft−lb.

DPlace the remaining Teflon washer around the other end of the check expansion valve. Lightly lubricate connector threads and expose sur- face of the Teflon ring with refrigerant oil.

EAttach the liquid line assembly to the check expansion valve. Finger tighten and use an appropriately sized wrench to turn an additional 1/2 turn clockwise as illustrated in the figure above or 20 ft−lb.

VAPOR LINE

ON LINES SMALLER THAN 7/8",

MOUNT SENSING BULB AT

 

 

EITHER THE 3 OR 9 O’CLOCK

 

POSITION.

 

12

BULB

BULB

SENSING BULB INSTALLATION

A Attach the vapor line sensing bulb in the proper orientation

VAPOR LINE

 

 

ON 7/8" AND LARGER LINES,

as illustrated to the right using the clamp and screws pro-

 

 

MOUNT SENSING BULB AT

vided.

 

 

EITHER THE 4 OR 8 O’CLOCK

NOTE

 

POSITION. NEVER MOUNT ON

12

BOTTOM OF LINE.

and check expansion bulb before insulating the sensing bulb

 

 

once installed.

1/8 TURN

 

BConnect the equalizer line from the check expansion valve to the equalizer vapor port on the vapor line. Finger tighten the flare nut plus 1/8 turn (7 ft−lbs) as illus- trated below.

11

12

1

10

 

2

9

 

3

84

7 6 5

BULB

BULB

 

NOTE OM OF LINE.

 

FLARE SEAL CAP

FLARE NUT

EQUALIZER LINE INSTALLATION

ARemove and discard either the flare seal cap or flare nut with copper flare seal bonnet from the equalizer line port on the vapor line as illustrated in the figure to the right.

BRemove and discard either the flare seal cap or flare nut with copper flare seal bonnet from the equalizer line port on the vapor line as illustrated in the figure to the right.

OR

COPPER FLARE

SEAL BONNET

 

 

MALE BRASS EQUALIZER

 

LINE FITTING

 

VAPOR LINE

Page 15

XC17 SERIES

Page 15
Image 15
Lennox International Inc Dave Lennox Signature Collection XC17 Air Conditioner Flushing Line SET and Indoor Coil 2