Installation and Configuration
6.0INSTALLATION AND CONFIGURATION
This section includes instructions on how to install, configure and perform initial electrical checks of your UPS installation.
DO NOT attempt to start the UPS, turn on any circuit breaker or energize the input power until instructed to do so in 7.0 - Initial Startup and Electrical Checks.
Visually inspect the UPS for freight damage. Report damage to the carrier and your local dealer or Liebert representative.
! CAUTION
The UPS is heavy (see 14.0 - Specifications). Take proper precautions when lifting or moving it.
Install the UPS indoors in a controlled environment, where it cannot be accidentally turned off. Place it in an area of unrestricted airflow around the unit, away from water, flammable liquids, gases, cor- rosives and other conductive contaminants. Maintain a minimum clearance of 4" (100mm) in the front and rear of the UPS. Maintain an ambient temperature range of 32°F to 104°F (0°C to 40°C).
NOTE
UPS operation in sustained temperatures above 77°F (25°C) reduces battery life.
6.1Install the Main Cabinet
The
6.1.1Tower UPS Installation
When using the
If any external battery cabinets are added, they will include spacers to accommodate the additional cabinets (shown below, right).
Figure 2 Support base and spacers
End Bases
2U Spacer
Spacers added to support
4U Support Basebase to accommodate additional battery cabinets
Attach Bezels to Top
When used as a tower, the
1.Position the UPS so that the battery compartment is on the bottom.
2.Attach the top bezels by placing them on the mounting holes and sliding them toward the rear of the UPS.