Feeder Clean Out
Any feeder in the Slide Gate/Auger blending system can be emptied and refilled with a different material. To do a feeder clean out, the operator has to press the “Clean Out” icon key from the recipe screen (the first screen that appears on power up).
This screen will allow you to Open or Close the Feeder, Weigh Hopper, Mixer Knife Gate, Empty the Entire Blender, Start or Stop the Mixer Motor, Test the Alarm Output, Find out the Mixer Proximity Status and monitor the Current Hopper Weight.
Figure 47: Typical Manual Control Operator Screen
Open or Close
Feeder
Open or Close
Weigh Hopper
Start or Stop Mixer Motor
Open or Close Mixer Knife Gate
Test Alarm
Output
Low Level Prox Status
Empty Entire
Blender
Warning Message
Current Hopper Weight
Go back to Setup Directory
The dump valve opens as soon as the “Press to Open Feeder” key is pressed. This easy feeder clean out option also serves as a means for emptying a batch that is held in the weigh hopper if the “Press to Open Weigh Hopper” key is pressed when the blender is stopped. To open/close feeder numbers 2, 3, 4, 5 & 6 press the number next to “Press to Open Feeder” to select the feeder you desire to empty and the “Press to Close Feeder” key to close the dump valve. Touch the “Done” key to return to the recipe menu. After entering a recipe, the operator will restart the blending system, putting it back in normal operation.
Note: Before starting Slide Gate/Auger blending systems, each ingredient hopper in the current recipe must contain material! Virgin material must be loaded in hopper #1 and hopper #3 should only be used for regrind!!
Once the operator initiates the run mode of operation, the blending system controller will begin monitoring the mixer
Once the mixer
Each component is metered in the order specified by the “Metering Order” setup. See the Installation & Setup chapter for further details.
Once the final ingredient specified in the recipe has been metered into the weigh hopper, the controller will take a final weight reading of the weigh hopper. This will start the “Dump
Chapter 4: 3BOperation | 59 of 101 |