Patton electronic 4400 manual Installing the power cables-DC units

Models: 4400

1 69
Download 69 pages 24.2 Kb
Page 32
Image 32

SmartNode 4400 Series Getting Started Guide

3 • Hardware installation

 

 

2.Rotate the power cable retainer clip so it secures the power cable plug in the IEC-320 connector as shown in figure 12.

Power cable

retainer clip

Grounding stud

Figure 12. Grounding stud and power cable retainer clip

3.Repeat steps 1 and 2 to install the remaining power cable.

4.Verify that the AC power cord included with your IpChannel Bank is compatible with local standards. If it is not, refer to chapter 5, “Contacting Patton for assistance” on page 44 to find out how to replace it with compatible power cord.

5.Connect the male end of the power cord to an appropriate power outlet.

6.Verify that the green POWER LED is lit.

Hardware installation is complete. Refer to chapter 4, “Getting started with the SmartNode 4400 Series” on page 34.

Installing the power cables—DC units

Mains Voltage: Do not open the case the when the power cord is attached. Line voltages are present within the power supply when the power cords are

connected. The mains outlet that is utilized to power the devise shall be WARNING within 10 feet (3 meters) of the device, shall be easily accessible, and pro-

tected by a circuit breaker.

Installing the IpChannel Bank

32

Page 32
Image 32