Introduction

This appendix lists the tasks for installing a SmartNode 4400 IpChannel Bank (see table 12). Make a copy of this checklist and mark the entries as you complete each task. For each IpChannel Bank, include a copy of the completed checklist in your site log.

Table 12. Installation checklist

Task

Verified by

Date

 

 

 

Network information available & recorded in site log

 

 

 

 

 

Environmental specifications verified

 

 

 

 

 

Site power voltages verified

 

 

 

 

 

Installation site pre-power check completed

 

 

 

 

 

Required tools available

 

 

 

 

 

Additional equipment available

 

 

 

 

 

All printed documents available

 

 

 

 

 

SmartWare release & build number verified

 

 

 

 

 

Rack, desktop, or wall mounting of chassis completed

 

 

 

 

 

Initial electrical connections established

 

 

 

 

 

ASCII terminal attached to console port

 

 

 

 

 

Cable length limits verified

 

 

 

 

 

Initial configuration performed

 

 

 

 

 

Initial operation verified

 

 

 

 

 