Installation
UPS Setup
When the UPS is in use, allow a minimum of 4 inches (100 mm) for ventilation on both sides, top, and rear of the UPS (see Figure 3). When the UPS is serviced, allow 30 inches (762 mm) for removal of the UPS left panel. Maintain clearance in front of the UPS for user operations. If you have an optional Power Distribution Module (PDM), allow additional space in the rear for the PDM cord connections.
PDM Cord Connections |
|
|
|
|
|
|
|
| 5.02 PDM Depth |
|
| 32 Minimum Spacing | |
|
|
|
|
| ||
| PDM |
|
|
| Around EBC | |
302 |
|
|
|
|
|
|
Clearance | UPS | EBC | EBC |
| EBC |
|
for Service |
|
|
|
|
|
|
|
|
|
|
|
|
|
42 Minimum Spacing
Around UPS
Figure 3. Spacing Requirements (Top View)
Floor Loading
When planning the installation, consider the UPS weight for floor loading. The strength of the installation surface must be adequate for point and distributed loadings. The weights are shown in the following table.
Standard Model Floor Loadings
Powerware 9150 | Maximum | Point Loading | Distributed |
| Weight (lb) | (lb/in2) | Loading (lb/ft2) |
Model 8 kVA | 550 | 12.5 | 170 |
|
|
|
|
Model 10 kVA | 550 | 12.5 | 170 |
|
|
|
|
Model 12.5 kVA | 550 | 12.5 | 170 |
|
|
|
|
468 | 9.6 | 130 | |
|
|
|
|
765 | 17.4 | 236 | |
|
|
|
|
18 | Powerware® 9150 User’s Guide : www.powerware.com |