Installation

Selecting an Installation Option

In addition to the standard Powerware 9150, the UPS has an optional PDM. Use the following flow chart to decide which installation option is right for you.

Do you have an

Yes

See “UPS with

Optional PDM

optional PDM?

 

Installation”

 

 

 

 

on page 25.

 

No

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

See the following

 

 

 

section, “UPS

 

 

 

Installation.”

 

 

 

 

 

 

 

 

UPS Installation

The Powerware 9150 has the following power connections:

:2-phase (L1/A and L2/B), neutral, and ground connection for rectifier/bypass input

:2-phase (L1/A and L2/B), neutral, and ground connection for load output

The nominal input/output voltages are:

:100/200, 110/220, or 120/240 Vac with 180phase displacement

:120/208 or 127/220 Vac with 120phase displacement

W A R N I N G

Only qualified service personnel (such as a licensed electrician) should perform the UPS installation and initial startup. Risk of electrical shock.

20

Powerware® 9150 User’s Guide : www.powerware.com