9.3 Outage Simulation Test

You should perform a test of whether the UPS operates properly during a power outage. Proper operation is as described below.

Note

Perform this test before powering the connected load devices on.

Set the breaker on your utility power breaker panel to “Off”.

Buzzer

 

2 beeps..., 2 beeps..., repeated

 

LEDs

 

Green INPUT

Blinking

Green INV.ON/STAND BY

Lit

Green OUTPUT

Lit

Set the breaker on your utility power breaker panel to “On”.

Buzzer

 

Silent

 

LEDs

 

Green INPUT

Lit

Green INV.ON/STAND BY

Lit

Green OUTPUT

Lit

Note

If your utility power breaker panel is too far away to access conveniently, you can also perform the test by setting MAIN SW to the “OFF” and “ON” positions.

Because the UPS continues inverter operation, there is a small amount of voltage (under 30V) at the input plug. Do not unplug the plug during operation.