Start Up and Operation

5

Start Up and Operation

 

 

5-1 Pre-Operational Checklist

To ensure the granulator is ready for operation, perform the tasks listed on the following pre-operational checklist. Make sure that all electrical and mechanical machine elements are inspected and any defects corrected first.

￿Have all installation and preparation instructions been read and followed?

￿Have the granulator operators and all other necessary personnel, such as the cleanout, maintenance and service persons, been fully trained on machine operation and all machine safety mechanisms?

￿Have the granulator operator and all other necessary personnel, such as the cleanout, maintenance and service persons, read the Operation and Installation Manual?

￿Have sufficient location clearances been allowed?

￿Has the equipment been grounded as required by local codes and/or Article 250 of the National Electric Code?

￿Have all motors been checked for proper rotation?

￿Have all machine controls, pushbuttons, and limit switch interlocks been checked for proper functioning?

￿Has the cutting chamber been checked for foreign matter?

￿Have the drive components been checked for alignment and tension?

￿Is the machine properly closed with all visible fasteners tight?

￿Are all accessory components electrically and mechanically connected with proper support and with all fasteners tight?

￿Are all electrical enclosure boxes tightly closed and clamped shut?

￿Are all personnel clear of the machine?