Chapter 3: Installation

3-1 Uncrating

2-Pump, 20-Station Controllers are shipped mounted on a skid, enclosed in a plastic wrapper, and contained in a cardboard box.

1. Pry the crating away from the skid.

Note: Remove the nails holding the box to the skid and lift the box off carefully; avoiding staples in the 1’ x 4’ wood supports. Cut the steel banding.

2.Use a pry bar to remove the blocks securing the unit to the skid.

3.Lift unit from sides, inserting forklift under the base. The forks must be equidistant from the centerline of the unit and the unit must be balanced on the forks. Lift slowly and only high enough to clear the skid. Use a pry bar if necessary to carefully remove the skid from the unit.

4.Lower slowly.

3-2 Mounting the Control Panel

Note: Before you mount the panel, consider how you will route wiring to the vacuum hoppers, the filter chamber atmospheric valve (if so equipped) and the pump motor starter(s), vacuum switch(es), and vent valve(s).

Mount the panel on a flat, vertical area. It should be a visible area that gives your operator access to the control. The panel requires a low voltage power drop as listed on the serial tag.

Hopper Loaders with/without Sight Glasses

10

Page 15
Image 15
Sterling Plumbing scc2 specifications Installation, Uncrating, Mounting the Control Panel