The cable clamp, shown on Page
The
To install a Patch Module with distribution cable, proceed as follows:
1.Open rear door.
2.Remove cable entrance dock at bottom of the cabinet, shown on Page
3.
Patch Modules will be installed from the top position (Patch Module 1) to the bottom (Patch Module 6). Unless otherwise direct- ed by operating company guidelines, prefer to start with the first distribution
Determine the length of the subunit breakout between the
NOTE
Telect only breaks out about 7 in. (~175 mm) of subunit. This would be for the shortest breakout from a cable clamp near the center of the cable entrance dock to Patch Module 6. The longest breakout would be about 64 in (~1600 mm) between a cable clamp near the left wall (viewed from the front of the cabinet) to Patch Module 1.
All cables entering the cabinet directly below the patch module rack need to be broken out at the cable clamp. The cable is not flexible enough to manipulate it below the rack and around to the distribution
4.Breakout subunits, heat shrink breakout, and then feed the opposite end of the cable into the distribution
5.Move the cable clamp down to approximately where the cable will enter the bottom of the cabinet.
NOTE
Before connecting, splicing, storing, or parking distribution pigtails at the home, office, or node, install the Patch Module in the cabinet, as detailed in the following procedure. Refer to the following illustration.
6.If necessary, provide temporary strain relief while handling and installing Patch Module by, for example, loosely tying down the cable at a convenient lance along a
7.Swing out hinged bulkhead from patch module’s anchor plate so that bulkhead fits through rack into front compartment. Then, secure anchor plate to partition wall using three acorn nuts provided.
8.Secure cable and subunit to distribution cable
Don’t use cable ties closer than about 1 ft (~300 mm) from the floor of the cabinet until all feeder and distribution cables are in- stalled. You’ll need some wiggle room for
9.At bottom of cabinet, adjust position of cable clamp in relationship to the cable entrance dock. Don’t secure the entrance dock until all scheduled distribution cables and Patch Modules are installed.
Telect, Inc. • USA +1.509.926.6000 • Mexico +1.52.33.3836.3700 |
|
Poland +1.48.713.239.100 • UK +1.44.1489.889500 • www.telect.com | Page |
Copyright © 2002 Telect, Inc., All Rights Reserved |