To use the
a.The furcation block has about 1.5 m (~5 ft) of transparent tubing for 900 µm fi- bers. Cut the transparent tubing back to 11½ in.(~300 mm).
b.Slip the fibers through the furcation block and transparent tubes and move the ends of the transparent tubes up to the SC/APC connectors.
c.Next, slip on the
d.Place the furcation block onto the bottom cover.
e.Snap on the top cover.
f.Slide up the
5.Secure ends of both distribution tubes at opposite entrances to the cassette, route fiber throughout cassette (Page
6.Record terminations on designation label included with cassette.
7.Finish all splices in a cassette before moving to the next.
Transparent Tubes | Loose Tubing |
Furcation Block
Bottom Cover
8.Continue with the remainder of the fibers from the distribution cable — splicing them to connectorized fibers — before moving to the next cable.
After every 72 fibers (6
6
Per Patch Module
9.Complete all cassettes in a pod before mounting the pod to the rear door and before routing the loose tubing.
Telect, Inc. • USA +1.509.926.6000 • Mexico +1.52.33.3836.3700
Poland +1.48.713.239.100 • UK +1.44.1489.889500 • www.telect.com
Copyright © 2002 Telect, Inc., All Rights Reserved | Page |