NOTE: The valve box assembly must be installed in the same room as the fireplace.

1.Choose the unit location.

2.The unit is shipped with four (4) nailing flanges mounted near the front corners on the side with the valve box assembly . (Fig. 4)

3.Frame the fireplace with a header across the top of the standoff. (Fig. 5) It is very important to allow for the finished wall face along with marble, tiles or any

Bend

Line

6"

1"

(25 mm) Min.

(152 mm) Min.

 

other noncombustible face finish material desired when setting the depth of the framing.

4.Attach the fireplace nailing flanges to the frame as shown in Figure 4.

5.The gas components are located in the control panel assembly attached to the right side of the unit. Choose the desired location on the wall or mantel for the valve box assembly. The conduit length is 5’ (1524 mm). (Fig. 6) The framing dimensions for the box are 12¹⁄”L x 9¹⁄”W x 5⁵⁄”D (311 x 235 x 143 mm). When the framing for the box is complete, remove the screws securing the valve box to the outer cas- ing. Carefully remove the valve box and, without stressing the conduit, slide the box into the framed opening. Replace the screws removed from the side of the outer casing.

������������

1���"

(38mm)

Max. Hearth Height

Fig. 4 Nailing flanges.

FP1357a

Fig. 6 Valve box assembly location.

6. To secure the valve box assembly to the framing

members, open the box door, remove extension

knob(s), remove the valve cover by removing the

two (2) screws securing the valve cover to the box,

hold the cover plate with one hand and disconnect

the wires to the switch and pilot indicator (R models

only). NOTE: Do not allow the valve cover plate to

hang from the pilot indicator wires as this could dam-

age the wires. Secure the box to the framing through

the two (2) holes at the top and one (1) on each

side using sheet rock screws. (Fig. 7) After fram-

ing the box, replace the wires, the valve cover, the

extension knob(s) in reverse order. NOTE: The pilot

indicator body is labelled +/-, make sure the positive

wire on the pilot indicator goes to ground and the

negative goes to the plug between the valve and the

thermocouple.

7. The U-channel located on the top of the unit as well

1" (25 mm)

6"

FP1467a

(152 mm)

Fig. 5 Fireplace framing.

as the nailing flanges on the sides that were men-

tioned in Step 1, are designed to accommodate non-

combustible board (recommended Dura-Rock). They

are positioned 1” (25mm) back from the face of the

unit. NOTE: The U-channel depth can be adjusted

by loosening the hex nut inside the channel.