Installation

To make the neutral connections:

1.Create only one neutral-to-ground bond in the system. In this case, it would be in the main AC distribution panel.

Important: Ensure there is only one neutral-to-ground bond in the entire system. See the Sine Wave Plus Inverter/Charger Owner’s Manual for additional information regarding the neutral-to-ground bond requirements.

2.Connect the neutral (white) wire from neutral bar in the AC distribution panel to one of the neutral terminals in the ACCB.

3.Connect the factory-installed neutral wire (white) in the ACCB to the NEU2 terminal in the inverter.

4.Connect the neutral (white) wire from the generator and connect it to one of the neutral terminals in the ACCB.

4

 

 

 

3

1

2

 

Figure 1-16Neutral Connections for an Off-Grid Application with an AC Distribution Panel and an External Generator Disconnect