Wiring for Off-Grid Applications using an AC Distribution Panel and an Internal Generator Disconnect

To make the ground connections:

1.Prepare the primary system ground and connect it to the ground bar in the main AC distribution panel. See the Sine Wave Plus Inverter/ Charger Owner’s Manual for information regarding preparing the primary system ground.

2.Route cable(s) (hot, neutral, and ground) from the AC distribution panel through one of the knockouts prepared in the ACCB and connect the ground wire (green) to the ground bar in the ACCB.

3.Connect the factory-installed ground wire (green) in the ACCB to the AC ground bar in the inverter.

4.Prepare the cabling from the generator. Route cable(s) (hot, neutral, and ground) from the generator into one of the knockouts prepared in the ACCB. Connect the ground wire (green) from the generator to the ground bar in the ACCB.

4

23

1

Figure 1-19Ground Connections for an Off-Grid Application with an AC Distribution Panel and an Internal Generator Disconnect Breaker

975-0046-01-01

1–23