Installation

To make the neutral connections:

1.Create only one neutral-to-ground bond in the system. In this case, it would be in the ACCB.

Important: Ensure there is only one neutral-to-ground bond in the entire system. See the Sine Wave Plus Inverter/Charger Owner’s Manual for additional information regarding the neutral-to-ground bond requirements.

2.Connect the factory-installed neutral wire (white) in the ACCB to the NEU2 terminal in the inverter.

3.Connect the neutral (white) wire from the generator (or generator disconnect) and connect it to one of the neutral terminals in the ACCB.

4.Route and connect a neutral wire from one of the neutral connections in the ACCB to the outlet that will support the AC load.

3

4

2

1

Figure 1-24Neutral Connections for an Off-grid Application with Additional Circuit Breakers in the ACCB

1–28

975-0046-01-01