Raypak 992B-1262B manual Table D Vent/Air Inlet Termination Clearances

Page 10

Fig. 6: Minimum Clearances from Vent/Air Inlet Terminations – Indoor and Outdoor Installations

 

 

U.S. Installations1

Canadian Installations2

 

 

 

 

A

Clearance above grade, veranda, porch,

1 ft (30 cm)

1 ft (30 cm)

deck, or balcony

 

 

 

 

 

 

 

 

Clearance to window or door that may be

4 ft (1.2m) below or to side

 

B

of opening; 1 foot (30 cm)

3 ft (91 cm)

opened

 

above opening

 

 

 

 

 

 

 

 

C

Clearance to permanently closed window

*

*

 

 

 

 

 

Vertical clearance to ventilated soffit located

 

 

D

above the terminal within a horizontal dis-

5 ft (1.5m)

*

tance of 2 ft (61cm) from the centerline of the

 

 

 

 

terminal

 

 

 

 

 

 

E

Clearance to unventilated soffit

*

*

 

 

 

 

F

Clearance to outside corner

*

*

 

 

 

 

G

Clearance to inside corner

6 ft (1.83m)

*

 

 

 

 

 

Clearance to each side of center line ex-

 

3 ft (91 cm) within a height

H

*

15 ft above the me-

tended above meter/regulator assembly

 

 

ter/regulator assembly

 

 

 

 

 

 

 

I

Clearance to service regulator vent outlet

*

6 ft (1.83m)

 

 

 

 

 

Clearance to non-mechanical air supply inlet

4 ft (1.2m) below or to side

 

J

to building or the combustion air inlet to any

of opening; 1 ft (30 cm)

3 ft (91 cm)

 

other appliance

above opening

 

 

 

 

 

K

Clearance to mechanical air supply inlet

3 ft (91 cm) above if within

6 ft (1.83m)

10 ft (3m) horizontally

 

 

 

 

 

 

 

L

Clearance above paved sidewalk or paved

7 ft (2.13m)

7 ft (2.13m) t

driveway located on public property

 

 

 

 

 

 

 

M

Clearance under veranda, porch, deck or

*

12 in. (30 cm) TT

balcony

 

 

 

 

 

 

 

1In accordance with the current ANSI Z223.1/NFPA 54 National Fuel Gas Code

2In accordance with the current CAN/CGA-B149 Installation Codes

t Vent terminal shall not terminate directly above sidewalk or paved driveway located between 2 single family dwellings that serves both dwellings

TT Permitted only if veranda, porch, deck, or balcony is fully open on a minimum of two sides beneath the floor and top of terminal and underside of veranda, porch, deck or balcony is greater than 1 ft (30cm)

*Clearances in accordance with local installation codes and the requirements of the gas supplier

Table D: Vent/Air Inlet Termination Clearances

10

Image 10
Contents Installation & Operating Instructions Page Contents Pay Attention to These Terms Product Receipt Before InstallationInstallations at Elevation Model IdentificationComponent Locations Component Locations BackValves General InformationModel Quantity Vent Size Gas Burners Blowers Model Burners per Valve Stages Fire at StageTime/Temperature Relationships in Scalds General SafetyWater Time to Produce Serious Temp Burn Equipment Base InstallationInstallation Codes StackingTable D Vent/Air Inlet Termination Clearances Outdoor Installations Indoor InstallationsClearances Reversing Air Filter Combustion and Ventilation AirIndoor Units Direct VentTruSeal Combustion Air InstallationsConventional Combustion Air Supply All Air from Inside the BuildingGeneral Canadian InstallationsWater Piping Reversing Water ConnectionsRelief Valve Piping Hydrostatic Test Cold Water OperationHydronic Heating Temperature & Pressure GaugePump Selection Air-Separation/Expansion Tank Pressure Drop in Feet of Head Feedwater RegulatorPiping Three-Way ValvesPotable Water and Space Heating Pool HeatingAutomatic Chlorinators and Chemical Feeders Winterizing Your HeaterPH of Water Gas SupplyPool/Spa Water Chemistry Water Hardness Total Dissolved SolidsModel Gas Supply ConnectionReversing Gas Supply Connection Table I Maximum Equivalent Pipe LengthGas Supply Pressure Electrical Power ConnectionsCheck the Power Source Field-Connected ControllersField Wiring Connection Making the Electrical ConnectionsOn-Off Wiring Connections Model Diameter Order Number VentingFlue Exhaust Tee Appliance CategoriesCombustion Exhaust Support of Vent StackVent Terminal Location Certified Combustion AirCanadian Installations InstallationsChanging the Flue Outlet Installation Venting Installation TipsVenting Configurations Natural Draft Vertical Venting CategoryCertified Vertical Venting Combustion Air Air Inlet Model TerminationCommon Venting System HeightHorizontal Through-the-Wall Venting Category Horizontal Through-the-Wall Venting CategoryVenting Direct Vent Horizontal Through- the-WallModel Certified Maximum Combustion Air Inlet Equivalent Material Vent Length Intake PipeDirect Vent Vertical Direct Vent VerticalControls Outdoor InstallationFreeze Protection Heater Sequence of Operation Models 992B-1262BExternal Lights Color Indication Models 1532B 1802B Page Page Models 2002B 2342B Page Page Ignition Module High Limit Manual ResetFlow Switch Operating ControlHigh and Low Gas Pressure Switches Low Water Cut-Off OptionalUDB Diagnostic Board UDB Fault HistoryWater Piping 87%-Efficiency Boilers Special InstructionsVenting Appliance Categories Vent Terminal Location Vertical Venting CategoryCondensate Management Equivalent Certified Maximum Combustion Air Air Inlet Model VentingMax. Length Material Vent Length Direct Vent Horizontal Through- the-Wall 992BE 75’ 100’ 1262BE Galvanized Steel 1532BE Category 25’ Wiring Diagram Models 992B-1262B Wiring Diagram Models 1532B-2342B START-UP Pre Start-upMain Burner Adjustment Blower AdjustmentStart-Up Follow-Up Safety InspectionLeak Test Procedure Dual-Seat Gas Valves Pilot Turn-Down TestPost Start-Up Check Leak TestLighting Instructions OperationTo Turn Off Gas To Appliance Troubleshooting StepSuggested Minimum Maintenance Schedule MaintenancePreventive Maintenance Schedule Annually WeeklySemi-Annually As RequiredAppendix Inside Air ContaminationLimited Parts Warranty HI Delta Types H and WH Limited Parts Warranty HI Delta Type P START-UP Checklist for FAN-ASSISTED Raypak Products Page