Raypak 992B-1262B manual Start-Up, Blower Adjustment, Main Burner Adjustment

Page 53

Preparation

WARNING: Do not turn on gas at this time.

Check Power Supply

With multi-meter at incoming power, check voltage between:

Hot - Common (≈120 VAC)

Hot - Ground (≈120 VAC)

Common - Ground (< 1 VAC)

WARNING: If Common - Ground is > 1 VAC,

STOP: Contact electrician to correct ground failure. Failure to do this may burn out 120V-24V transformer, or may cause other safety control damage or failure.

Attach Manometers to Measure Pressures

1.Turn off main gas valve.

2.Attach 24” scale manometer to the first main gas shut-off valve pressure tapping.

3.Attach (1) 12” scale manometer to the outlet side of the second main gas shut-off valve pressure tapping.

4.Attach (1) 12” scale manometer near the fan-prov- ing switch. Pull black cap from air pressure switch tee and connect the manometer. NOTE: Retain caps for reinstallation later.

Check Gas Supply Pressure

1.Slowly turn on main gas shut-off valve.

2.Read the gas supply pressure from the manome- ter; minimum supply pressure for natural gas is 5.0 in. WC, recommended supply is 7.0 in. WC, mini- mum supply pressure for propane gas is 11.0 in. WC (dynamic readings, all stages firing).

3.If the pressure is > 14.0 in. WC, turn off the valve.

4.Check if the service regulator is installed and/or adjust the service regulator.

Start-Up

Blower Adjustment

1.Turn off power.

2.Unplug cap at pressure switches and connect ma- nometer(s) to the tee.

3.Close all manual firing valves.

4.Turn power on.

5.Check manometers attached to fan pressure switch. The reading should be 1.4 ± .1 in. WC for propane gas and natural gas. If not, adjust the air shutter on the blowers to attain the correct value.

6.Turn power off.

7.Reconnect this cap.

Main Burner Adjustment

1.Turn off unit.

2.Open manual firing valves.

3.Turn on the unit, wait 15 seconds, and the igniter should glow. Look into sight glass located at each end of the heater to check igniter operation. Gas valves should open in 45-60 seconds.

4.If burner does not light on first trial. It will retry, up to three times.

5.Main burner ignition: Check manifold gas pressure at gas valve outlet pressure tap. This should read 3.5 ± 0.1 in. WC for natural gas and 10.5 ± 0.1 in. WC for propane gas.

6.If the pressure reading differs by more than ± 0.1 in. WC, remove screw cover from the gas pres- sure regulator and adjust main burner manifold pressure. Replace the screw cover. Repeat steps 2 to 5 on other valves as necessary.

CAUTION: Special manifold and air settings may be required. Verify rating plate and blower housing.

53

Image 53
Contents Installation & Operating Instructions Page Contents Pay Attention to These Terms Installations at Elevation Before InstallationProduct Receipt Model IdentificationComponent Locations Back Component LocationsModel Quantity Vent Size Gas Burners Blowers General InformationValves Model Burners per Valve Stages Fire at StageWater Time to Produce Serious Temp Burn General SafetyTime/Temperature Relationships in Scalds Installation Codes InstallationEquipment Base StackingTable D Vent/Air Inlet Termination Clearances Clearances Indoor InstallationsOutdoor Installations Indoor Units Combustion and Ventilation AirReversing Air Filter Direct VentConventional Combustion Air Supply InstallationsTruSeal Combustion Air All Air from Inside the BuildingWater Piping Canadian InstallationsGeneral Reversing Water ConnectionsCold Water Operation Relief Valve Piping Hydrostatic TestPump Selection Temperature & Pressure GaugeHydronic Heating Piping Pressure Drop in Feet of Head Feedwater RegulatorAir-Separation/Expansion Tank Three-Way ValvesPool Heating Potable Water and Space HeatingWinterizing Your Heater Automatic Chlorinators and Chemical FeedersPool/Spa Water Chemistry Water Hardness Gas SupplyPH of Water Total Dissolved SolidsReversing Gas Supply Connection Gas Supply ConnectionModel Table I Maximum Equivalent Pipe LengthCheck the Power Source Electrical Power ConnectionsGas Supply Pressure Field-Connected ControllersMaking the Electrical Connections Field Wiring ConnectionOn-Off Wiring Connections Flue Exhaust Tee VentingModel Diameter Order Number Appliance CategoriesVent Terminal Location Support of Vent StackCombustion Exhaust Certified Combustion AirChanging the Flue Outlet InstallationsCanadian Installations Venting Configurations Venting Installation TipsInstallation Natural Draft Vertical Venting CategoryCommon Venting System TerminationCertified Vertical Venting Combustion Air Air Inlet Model HeightHorizontal Through-the-Wall Venting Category Horizontal Through-the-Wall Venting CategoryModel Certified Maximum Combustion Air Inlet Direct Vent Horizontal Through- the-WallVenting Equivalent Material Vent Length Intake PipeDirect Vent Vertical Direct Vent VerticalFreeze Protection Outdoor InstallationControls Models 992B-1262B Heater Sequence of OperationExternal Lights Color Indication Models 1532B 1802B Page Page Models 2002B 2342B Page Page Flow Switch High Limit Manual ResetIgnition Module Operating ControlLow Water Cut-Off Optional High and Low Gas Pressure SwitchesUDB Fault History UDB Diagnostic BoardVenting Appliance Categories 87%-Efficiency Boilers Special InstructionsWater Piping Condensate Management Vertical Venting CategoryVent Terminal Location Max. Length Material Vent Length Certified Maximum Combustion Air Air Inlet Model VentingEquivalent Direct Vent Horizontal Through- the-Wall 992BE 75’ 100’ 1262BE Galvanized Steel 1532BE Category 25’ Wiring Diagram Models 992B-1262B Wiring Diagram Models 1532B-2342B Pre Start-up START-UPStart-Up Blower AdjustmentMain Burner Adjustment Leak Test Procedure Dual-Seat Gas Valves Safety InspectionFollow-Up Pilot Turn-Down TestLeak Test Post Start-Up CheckTo Turn Off Gas To Appliance OperationLighting Instructions Step TroubleshootingPreventive Maintenance Schedule MaintenanceSuggested Minimum Maintenance Schedule Semi-Annually WeeklyAnnually As RequiredInside Air Contamination AppendixLimited Parts Warranty HI Delta Types H and WH Limited Parts Warranty HI Delta Type P START-UP Checklist for FAN-ASSISTED Raypak Products Page