Xantrex Technology PV100S-480 installation manual System Specifications, Electrical Specifications

Page 24

Introduction

System Specifications

The PV100S has been designed for photovoltaic power systems, which operate within the following specifications.

CAUTION: Equipment Damage

Operation of the PV100S in a manner other than specified in this manual may cause damage to the PV100S and other system components and will void the terms of the warranty.

Electrical Specifications

Table 1-1 provides the AC and DC specifications for the PV100S.

Table 1-1Electrical Specifications

Specification

PV100S-208

PV100S-480

 

 

 

Nominal AC Input Voltage

208 Vac

480 Vac

(+10% to -12% acceptable range)

(183 to 228 Vac)

(422 to 528 Vac)

Maximum AC Output Current

278 Arms

121 Arms

Nominal AC Input Frequency

60 Hz

60 Hz

(+0.5 to -0.7 Hz acceptable range)

(59.3 to 60.5 Hz)

(59.3 to 60.5 Hz)

Output Power

100.0 kW

100.0 kW

Peak Power Tracking Window

330 to 600 Vdc

330 to 600 Vdc

Maximum Open Circuit Voltage

600 Vdc

600 Vdc

Maximum DC Input Current

319 amps

319 amps

 

 

 

Over Voltage, Under Voltage and Frequency Ranges

Table 1-2 provides the over voltage, under voltage, over-frequency, and under-frequency detection limits for the PV100S. These detection limits have been factory tested and deemed to be in compliance with IEEE-929 and UL 1741 requirements for utility interaction.

Table 1-2Over/Under Voltage and Over/Under Frequency Ranges

 

 

PV100S-208

 

PV100S-480

Vac Condition

 

 

 

 

 

 

 

 

 

 

 

 

(% of Nominal)

Voltage Range

Trip Time

Voltage Range

Trip Time

 

 

 

 

 

Vac < 50%

Vac < 104

6 cycles

Vac < 240

6 cycles

50% < Vac < 88%

104

< Vac < 183

2 seconds

240

< Vac < 422

2 seconds

88% < Vac < 110%

183

< Vac < 228

normal operation

422

< Vac < 528

normal operation

110% < Vac < 137%

228

< Vac < 285

2 seconds

528

< Vac < 657

2 seconds

137% < Vac

285

< Vac

2 cycles

657

< Vac

2 cycles

f < rated -0.7

f < 59.3

6 cycles

f < 59.3

6 cycles

f > rated +0.5

f > 60.5

6 cycles

f > 60.5

6 cycles

1–4

152315 Rev C

Image 24
Contents PV100S 100 kW Grid-Tied Photovoltaic Inverter Page PV100S 100 kW Grid-Tied Photovoltaic Inverter Date and Revision Purpose ScopeAudience OrganizationConventions Used Following conventions are used in this guideAbbreviations and Acronyms Related InformationPage Important Safety Instructions General Safety Precautions Personal SafetySafety Equipment Wiring RequirementsSafety Operational Safety Procedures Lockout and TagDe-Energize/Isolation Procedure Interconnection Standards ComplianceTo isolate the PV100S Xii Contents Installation SchematicsVerification Tables Xvi Figures Figures Introduction Description of the PV100S 1Dimensions Not to scale System Specifications Electrical SpecificationsSystem Ground Requirements Environmental Specifications 3Environmental SpecificationsMain Enclosure Door Interlock Switch Operator Interface ControlsOn/Off Switch 3On/Off SwitchCommunication Features AC and DC Disconnect SwitchesSystem Status and Fault Reporting Data LoggingCommunication Methods Universal Front Panel Control Unit UfcuPC Connection Methods 6PC Connections in the Communications EnclosurePots Access Ethernet LAN Access Planning Overview of PV100S Installation Ventilation and Serviceability Requirements PV PlanningGround Requirements System Neutral RequirementsCommunication Requirements Utility Side Isolation Transformer RequirementsElectrical Diagrams and Schematics Model PV100S-480Model PV100S-208 Layout Options 1PV100S Layout Option a2PV100S Layout Option B Conduit Penetration 3Conduit Entry Figure Reference15 cm 12 30 cm 10.5 27 cm Conductor and Conduit Sizing To calculate the proper conduit sizeDetermine the required cable ampacity Size the cable Size the conduitAnchoring the PV100S 29 73.7 cm 16 ¼ 40.6 cm10AC Interface/Transformer Anchor Bolt Pattern Not to Scale Installation Equipment Required UnloadingMoving the PV100S Unpacking the PV100STo move the PV100S using a forklift Removing the Pallet and Moving the PV100SMounting and Anchoring the Units To mount and anchor the PV100SOpening or Closing Access Doors To lock or unlock the front door on the main inverterTo Open Access Door To Close Access Door7Transformer Access Panels Conduit Installation To install the conduitsWiring General Overcurrent Protection Conductor TerminationWire Gauge and Torque Requirements GroundingSystem Neutral Requirements Utility Side Isolation Transformer RequirementsWiring Specific AC Connections13Tie-wraps on the AC Sense Harness 15AC Terminal Connections in the Main Inverter Enclosure 17Connecting the AC Sense Harness To connect the utility service to AC Interface Enclosure18AC Terminal Connections from the Utility PV Array Connections 19PV Array Cable Routing and TerminationsPC Communications To connect a personal computer using the Pots Connection Establishing a Pots ConnectionEstablishing Wireless Connection To connect a personal computer using the GSM Wireless modemIf connecting the PC directly to the inverter Direct Connection22Direct Connect Installation Verification Verification Procedure Summary Visual Inspection of Mechanical Connections Visual Inspection of Electrical ConnectionsVisual Inspection, Isolation Transformer Wye/Wye Corrective ActionPerform after initial inspection if required Schematics This page intentionally left blank Figure A-1Electrical Diagram sample Schematics Appendix a Schematics Appendix a Schematics Appendix a This page was intentionally left blank Index IX-2 Rev C Page Xantrex Technology Inc