Verification
Verification Procedure Summary
WARNING: Electrocution Hazard
This chapter describes specific steps to ensure the installation of the PV100S 100 kW
WARNING: Shock Hazard
The PV100S enclosures contain exposed
WARNING: Lethal Voltage
In order to remove all sources of voltage from the PV100S, the incoming power must be
The following procedures are intended to verify correct installation and proper wiring of the PV100S. Prior to performing the following verification steps on the PV100S, review all safety requirements and procedures outlined in this manual and on any cautionary markings on the components within the system.
Inspect the following items prior to completion of the installation:
1.Visually inspect all the mechanical connections. This would include both electrical conduit fittings, as well as enclosure anchoring and seismic bracing if required.
2.Visually inspect the electrical connections and verify proper tightness of all terminations.
3.Visually inspect the Isolation Transformer Wye/Wye connections and ensure the
4.Perform corrective actions if required.