Visual Inspection of Mechanical Connections

Visual Inspection of Mechanical Connections

To perform a visual inspection of the PV100S mechanical connections:

1.

Ensure that the AC and DC Disconnect Switches, as well as any utility

 

interconnect circuit breakers or main disconnect switches, are opened.

 

2.

Ensure all anchor bolts and any required seismic bracing is properly

 

tightened and in place.

 

3.

Remove the wiring access panels and front covers from the AC

 

Interface/Transformer assembly and Main Inverter Inductor Enclosure.

 

4.

Remove the latches and open the doors of the Main Inverter Enclosure,

 

the AC and DC Interface Enclosures, and Communication Enclosure

 

 

and inspect.

 

5.

Verify all wire conduit fittings and connections are properly tightened.

Visual Inspection of Electrical Connections

To perform a visual inspection of the PV100S electrical connections:

1.

Ensure that the AC and DC disconnect switches, as well as any utility

 

interconnect circuit breakers or main disconnect switches, are opened.

 

2.

Ensure all conductors and wiring connections interfacing with the

 

PV100S are tightened to the correct torque value.

 

 

For specific torque values, see Table 3-1, “AC Terminal Wire Gauge,

 

 

Bolt Size, and Torque Values” on page 3–12 and Table 3-2, “DC

 

 

Terminal Wire Gauge, Bolt Size, and Torque Values” on page 3–12.

 

3.

Verify AC power conductors terminated at TB4-A, TB4-B, TB4-C

 

within the Main Inverter Enclosure are terminated correctly and

 

 

properly sequenced.

 

4.

Verify the AC power conductors terminated at S1-2T1, S1-4T2, S1-6T3

 

within the AC Interface Enclosure are terminated correctly and properly

 

 

sequenced.

 

5.

Verify DC power conductors terminated at TB3-1, TB3-2, TB3-3 within

 

the DC Interface Enclosure are terminated correctly and properly

 

 

polarized.

 

152315 Rev C

4–3

Image 75
Contents PV100S 100 kW Grid-Tied Photovoltaic Inverter Page PV100S 100 kW Grid-Tied Photovoltaic Inverter Date and Revision Organization PurposeScope AudienceFollowing conventions are used in this guide Conventions UsedRelated Information Abbreviations and AcronymsPage Important Safety Instructions Wiring Requirements General Safety PrecautionsPersonal Safety Safety EquipmentSafety Lockout and Tag Operational Safety ProceduresDe-Energize/Isolation Procedure Interconnection Standards ComplianceTo isolate the PV100S Xii Contents Installation SchematicsVerification Tables Xvi Figures Figures Introduction Description of the PV100S 1Dimensions Not to scale Electrical Specifications System SpecificationsSystem Ground Requirements 3Environmental Specifications Environmental SpecificationsOperator Interface Controls Main Enclosure Door Interlock Switch3On/Off Switch On/Off SwitchAC and DC Disconnect Switches Communication FeaturesData Logging System Status and Fault ReportingUniversal Front Panel Control Unit Ufcu Communication Methods6PC Connections in the Communications Enclosure PC Connection MethodsPots Access Ethernet LAN Access Planning Overview of PV100S Installation PV Planning Ventilation and Serviceability RequirementsUtility Side Isolation Transformer Requirements Ground RequirementsSystem Neutral Requirements Communication RequirementsElectrical Diagrams and Schematics Model PV100S-480Model PV100S-208 1PV100S Layout Option a Layout Options2PV100S Layout Option B 3Conduit Entry Figure Reference Conduit Penetration15 cm 12 30 cm 10.5 27 cm Conductor and Conduit Sizing To calculate the proper conduit sizeDetermine the required cable ampacity Size the conduit Size the cable29 73.7 cm 16 ¼ 40.6 cm Anchoring the PV100S10AC Interface/Transformer Anchor Bolt Pattern Not to Scale Installation Unloading Equipment RequiredUnpacking the PV100S Moving the PV100SRemoving the Pallet and Moving the PV100S To move the PV100S using a forkliftTo mount and anchor the PV100S Mounting and Anchoring the UnitsTo lock or unlock the front door on the main inverter Opening or Closing Access DoorsTo Close Access Door To Open Access Door7Transformer Access Panels To install the conduits Conduit InstallationWiring General Conductor Termination Overcurrent ProtectionGrounding Wire Gauge and Torque RequirementsUtility Side Isolation Transformer Requirements System Neutral RequirementsAC Connections Wiring Specific13Tie-wraps on the AC Sense Harness 15AC Terminal Connections in the Main Inverter Enclosure To connect the utility service to AC Interface Enclosure 17Connecting the AC Sense Harness18AC Terminal Connections from the Utility 19PV Array Cable Routing and Terminations PV Array ConnectionsPC Communications Establishing a Pots Connection To connect a personal computer using the Pots ConnectionTo connect a personal computer using the GSM Wireless modem Establishing Wireless ConnectionDirect Connection If connecting the PC directly to the inverter22Direct Connect Installation Verification Verification Procedure Summary Visual Inspection of Electrical Connections Visual Inspection of Mechanical ConnectionsVisual Inspection, Isolation Transformer Wye/Wye Corrective ActionPerform after initial inspection if required Schematics This page intentionally left blank Figure A-1Electrical Diagram sample Schematics Appendix a Schematics Appendix a Schematics Appendix a This page was intentionally left blank Index IX-2 Rev C Page Xantrex Technology Inc