Xantrex Technology PV100S-480 installation manual System Status and Fault Reporting, Data Logging

Page 30

Introduction

System Status and Fault Reporting

Basic system status and all fault conditions rising from within the PV100S are reported to the UFCU. The unit stores the time and details of all faults in non-volatile memory. The 4-line LCD will display a hexadecimal value and a brief text description of the fault.

This information can also be accessed using a personal computer using the GUI software either directly or remotely. Alternatively, the fault reporting can be accomplished using the optional Fax Modem.

Types of status information include:

Current Operating State or Goal State

Fault Code (if applicable)

Inverter State

Line Voltage and Current

Inverter Matrix Temperature

Inverter Power

PV State

PV Voltage and Current

PV Power

Grid Frequency

Peak Power Tracker Enabled

Data Logging

The inverter stores data values and software metrics for debugging. These values are stored within the CCU2 controller board in non-volatile memory. Data logging requires the use of a PC connection using the Xantrex Solar Graphic User Interface (GUI) software.

The data logging features include the following.

Operational Values

Internal Metrics

Data Log Acquisition

Graphic Data Analysis

Fault Log Acquisition

Software Upgrade

Accumulated Values

Configurable Parameters

1–10

152315 Rev C

Image 30
Contents PV100S 100 kW Grid-Tied Photovoltaic Inverter Page PV100S 100 kW Grid-Tied Photovoltaic Inverter Date and Revision Audience PurposeScope OrganizationConventions Used Following conventions are used in this guideAbbreviations and Acronyms Related InformationPage Important Safety Instructions Safety Equipment General Safety PrecautionsPersonal Safety Wiring RequirementsSafety Operational Safety Procedures Lockout and TagDe-Energize/Isolation Procedure Interconnection Standards ComplianceTo isolate the PV100S Xii Contents Installation SchematicsVerification Tables Xvi Figures Figures Introduction Description of the PV100S 1Dimensions Not to scale System Specifications Electrical SpecificationsSystem Ground Requirements Environmental Specifications 3Environmental SpecificationsMain Enclosure Door Interlock Switch Operator Interface ControlsOn/Off Switch 3On/Off SwitchCommunication Features AC and DC Disconnect SwitchesSystem Status and Fault Reporting Data LoggingCommunication Methods Universal Front Panel Control Unit UfcuPC Connection Methods 6PC Connections in the Communications EnclosurePots Access Ethernet LAN Access Planning Overview of PV100S Installation Ventilation and Serviceability Requirements PV PlanningCommunication Requirements Ground RequirementsSystem Neutral Requirements Utility Side Isolation Transformer RequirementsElectrical Diagrams and Schematics Model PV100S-480Model PV100S-208 Layout Options 1PV100S Layout Option a2PV100S Layout Option B Conduit Penetration 3Conduit Entry Figure Reference15 cm 12 30 cm 10.5 27 cm Conductor and Conduit Sizing To calculate the proper conduit sizeDetermine the required cable ampacity Size the cable Size the conduitAnchoring the PV100S 29 73.7 cm 16 ¼ 40.6 cm10AC Interface/Transformer Anchor Bolt Pattern Not to Scale Installation Equipment Required UnloadingMoving the PV100S Unpacking the PV100STo move the PV100S using a forklift Removing the Pallet and Moving the PV100SMounting and Anchoring the Units To mount and anchor the PV100SOpening or Closing Access Doors To lock or unlock the front door on the main inverterTo Open Access Door To Close Access Door7Transformer Access Panels Conduit Installation To install the conduitsWiring General Overcurrent Protection Conductor TerminationWire Gauge and Torque Requirements GroundingSystem Neutral Requirements Utility Side Isolation Transformer RequirementsWiring Specific AC Connections13Tie-wraps on the AC Sense Harness 15AC Terminal Connections in the Main Inverter Enclosure 17Connecting the AC Sense Harness To connect the utility service to AC Interface Enclosure18AC Terminal Connections from the Utility PV Array Connections 19PV Array Cable Routing and TerminationsPC Communications To connect a personal computer using the Pots Connection Establishing a Pots ConnectionEstablishing Wireless Connection To connect a personal computer using the GSM Wireless modemIf connecting the PC directly to the inverter Direct Connection22Direct Connect Installation Verification Verification Procedure Summary Visual Inspection of Mechanical Connections Visual Inspection of Electrical ConnectionsVisual Inspection, Isolation Transformer Wye/Wye Corrective ActionPerform after initial inspection if required Schematics This page intentionally left blank Figure A-1Electrical Diagram sample Schematics Appendix a Schematics Appendix a Schematics Appendix a This page was intentionally left blank Index IX-2 Rev C Page Xantrex Technology Inc