PV Planning
Large gauge wire must conform to the minimum bend radius specified in the
NEC, Article
Take care to keep the wire bundles away from any sharp edges which may damage wire insulation over time.
All conductors should be made of copper and rated for 90 °C (minimum).
If the installation of the PV100S is to be outdoors, all interconnect conduit and fittings must be NEMA 4 rated as required by the NEC.
PV Planning
To determine the number of photovoltaic panels that are required for the PV power plant, please use the PV planning tool from the Xantrex website:
http://www.xantrex.com/support/pvsizing/disclaimer.asp
Ventilation and Serviceability Requirements
| The following environmental conditions must be established and maintained to |
| ensure the safe and efficient operation and servicing of the PV100S. Adequate |
| space must be provided around the unit for ventilation and access during |
| servicing. If locating the unit indoors, ambient air temperature cannot exceed the |
| maximum temperature for which the unit is rated. |
Ventilation | Maintain a minimum clearance of 12 inches on both sides and 6 inches behind the |
| Main Inverter Enclosure and the AC Interface Enclosure for proper cooling fan |
| operation. |
Maintenance and | Maintain a minimum clearance of 36 inches in front of the main inverter access |
Serviceability | door, the Transformer Enclosure access panel, and the AC interface access door |
| for maintenance and serviceability. |
| See Figure |
| clearance requirements. |
Indoor Temperature | If the PV100S is to be installed indoors and external air is used for ventilation, the |
Control | required cubic feet per minute (CFM) rate must be no less than 1000 CFM. This |
| assumes the temperature inside the building is allowed to rise only 10 °C above |
| the outside temperature. Therefore, the maximum allowable outside ambient |
| temperature is 50 °C (50 °C minus 10 °C equals 40 °C Maximum Ambient |
| Temperature). |
| If air conditioning is planned for an indoor installation, the heat load of the |
| PV100S is 1800 BTU/Hour at full load. |
152315 Rev C |