Xantrex Technology PV100S-480 installation manual Overview of PV100S Installation

Page 36

Planning

Overview of PV100S Installation

 

WARNING: Shock Hazard

 

Installations of this equipment should only be performed by qualified technicians.

 

Installers must meet all local and state code requirements for licensing and

 

training for the installation of Electrical Power Systems with AC and DC voltage

 

to 600 volts.

 

 

Planning

Planning for a system requires complete understanding of all the components that

 

are involved to successfully install the PV100S to meet the required national,

 

state, and local codes.

Definition

A power system (such as the PV100S) is a collection of devices designed to

 

supply AC power to the utility grid from a solar energy (PV) source.

Components

All types of grid-tied inverter installations, residential or industrial, share common

 

components. This chapter describes each component and suggests the minimum

 

requirements for a safe installation.

Location

The PV100S 100 kW Grid-Tied Photovoltaic Inverter is designed to be installed

 

in either an indoor or outdoor location. The PV100S must be anchored to a level,

 

concrete floor or pad.

 

Ideally the AC interface enclosure/transformer assembly is placed on the left side

 

of the Main Inverter Enclosure. The AC interface enclosure/transformer assembly

 

may be co-located adjacent to the left side of the Main Inverter Enclosure up to,

 

but not exceeding, 15 feet away.

Clearance

Adequate ventilation and service access must be taken into consideration when

 

installing the PV100S. See “Ventilation and Serviceability Requirements” on

 

page 2–3 for specific clearance requirements and ambient temperature

 

requirements.

Conduits and

Given the flexibility to co-locate the AC interface enclosure/transformer assembly

Conductors

to fit a desired system layout, the conduits and conductors are to be supplied by

 

the installer.

 

See “Conduit Penetration” on page 2–8 for recommendations on enclosure

 

penetration locations and conduit routing.

 

See “Conductor and Conduit Sizing” on page 2–11 for information on sizing the

 

conductors and conduits.

 

All interconnect wiring and power conductors interfacing to the PV100S must be

 

in accordance with the National Electric Code ANSI/NFPA 70 and any applicable

 

local codes.

2–2

152315 Rev C

Image 36
Contents PV100S 100 kW Grid-Tied Photovoltaic Inverter Page PV100S 100 kW Grid-Tied Photovoltaic Inverter Date and Revision Purpose ScopeAudience OrganizationConventions Used Following conventions are used in this guideAbbreviations and Acronyms Related InformationPage Important Safety Instructions General Safety Precautions Personal SafetySafety Equipment Wiring RequirementsSafety Operational Safety Procedures Lockout and TagDe-Energize/Isolation Procedure Interconnection Standards ComplianceTo isolate the PV100S Xii Contents Installation SchematicsVerification Tables Xvi Figures Figures Introduction Description of the PV100S 1Dimensions Not to scale System Specifications Electrical SpecificationsSystem Ground Requirements Environmental Specifications 3Environmental SpecificationsMain Enclosure Door Interlock Switch Operator Interface ControlsOn/Off Switch 3On/Off SwitchCommunication Features AC and DC Disconnect SwitchesSystem Status and Fault Reporting Data LoggingCommunication Methods Universal Front Panel Control Unit UfcuPC Connection Methods 6PC Connections in the Communications EnclosurePots Access Ethernet LAN Access Planning Overview of PV100S Installation Ventilation and Serviceability Requirements PV PlanningGround Requirements System Neutral RequirementsCommunication Requirements Utility Side Isolation Transformer RequirementsElectrical Diagrams and Schematics Model PV100S-480Model PV100S-208 Layout Options 1PV100S Layout Option a2PV100S Layout Option B Conduit Penetration 3Conduit Entry Figure Reference15 cm 12 30 cm 10.5 27 cm Conductor and Conduit Sizing To calculate the proper conduit sizeDetermine the required cable ampacity Size the cable Size the conduitAnchoring the PV100S 29 73.7 cm 16 ¼ 40.6 cm10AC Interface/Transformer Anchor Bolt Pattern Not to Scale Installation Equipment Required UnloadingMoving the PV100S Unpacking the PV100STo move the PV100S using a forklift Removing the Pallet and Moving the PV100SMounting and Anchoring the Units To mount and anchor the PV100SOpening or Closing Access Doors To lock or unlock the front door on the main inverterTo Open Access Door To Close Access Door7Transformer Access Panels Conduit Installation To install the conduitsWiring General Overcurrent Protection Conductor TerminationWire Gauge and Torque Requirements GroundingSystem Neutral Requirements Utility Side Isolation Transformer RequirementsWiring Specific AC Connections13Tie-wraps on the AC Sense Harness 15AC Terminal Connections in the Main Inverter Enclosure 17Connecting the AC Sense Harness To connect the utility service to AC Interface Enclosure18AC Terminal Connections from the Utility PV Array Connections 19PV Array Cable Routing and TerminationsPC Communications To connect a personal computer using the Pots Connection Establishing a Pots ConnectionEstablishing Wireless Connection To connect a personal computer using the GSM Wireless modemIf connecting the PC directly to the inverter Direct Connection22Direct Connect Installation Verification Verification Procedure Summary Visual Inspection of Mechanical Connections Visual Inspection of Electrical ConnectionsVisual Inspection, Isolation Transformer Wye/Wye Corrective ActionPerform after initial inspection if required Schematics This page intentionally left blank Figure A-1Electrical Diagram sample Schematics Appendix a Schematics Appendix a Schematics Appendix a This page was intentionally left blank Index IX-2 Rev C Page Xantrex Technology Inc